ARYAN ONE WING E AND F

by Konark Lifespaces Partnership
Certificate Signed P51700009247
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700009247
Registration No.
REA51700008029
Registration Date
2018-03-08
Developer
Konark Lifespaces Partnership
Architect
Architects Incorporate
Project Bank
SARASWAT COOPERATIVE BANK LIMITED
Proposed Possession
2018-04-30
Revised Possession
2018-04-30
Extended Possession
2019-03-31
Units Sold
0
Buildings
2
Project Area
2862.00 sq.m
Total FSI
6391.84
Approved FSI
6391.84
MahaRERA QR
ARYAN ONE WING E AND F
MahaRERA — P51700009247
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors12
Sanctioned12
🚗Open Parking79
🅿️Closed Parking35
📅Completion2018-04-30
🏗️Proposed Floors14
Sanctioned14
🚗Open Parking71
🅿️Closed Parking19
📅Completion2018-04-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
Residential 1 Bhk 31.1200008392334 0 0 0
0%
Residential 1 Bhk 31.809999465942383 0 0 0
0%
Residential 1 Bhk 32.34000015258789 0 0 0
0%
Residential 1 Bhk 32.599998474121094 0 0 0
0%
Residential 1 Bhk 32.7400016784668 0 0 0
0%
Residential 1 Bhk 32.81999969482422 0 0 0
0%
Residential 1 Bhk 33.209999084472656 0 0 0
0%
Residential 1 Bhk 33.220001220703125 0 0 0
0%
Residential 1 Bhk 33.290000915527344 0 0 0
0%
Residential 1 Bhk 33.459999084472656 0 0 0
0%

Aryan One Wing E

Type Carpet (sq.ft) Total Booked Available Status
RESIDENTIAL 1 BHK 31.12 10 9 1
90%
RESIDENTIAL 1 BHK 31.81 10 10 0
100%
RESIDENTIAL 1 BHK 32.34 10 3 7
30%
RESIDENTIAL 1 BHK 32.6 9 9 0
100%
RESIDENTIAL 1 BHK 32.74 4 1 3
25%
RESIDENTIAL 1 BHK 32.82 10 5 5
50%
RESIDENTIAL 1 BHK 33.21 1 1 0
100%
RESIDENTIAL 1 BHK 33.22 5 0 5
0%
RESIDENTIAL 1 BHK 33.29 10 9 1
90%
RESIDENTIAL 1 BHK 33.46 10 7 3
70%

Construction Progress

ARYAN ONE WING E

Basement (if any)100%

Aryan One Wing E

Excavation100%

ARYAN ONE WING E

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Aryan One Wing E

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

ARYAN ONE WING E

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Aryan One Wing E

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

ARYAN ONE WING E

Plinth100%
Podiums (if any) 0%

Aryan One Wing E

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

ARYAN ONE WING E

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Aryan One Wing E

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

ARYAN ONE WING E

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Aryan One Wing E

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

ARYAN ONE WING F

Basement (if any)100%

Aryan One Wing F

Excavation100%

ARYAN ONE WING F

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Aryan One Wing F

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

ARYAN ONE WING F

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Aryan One Wing F

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

ARYAN ONE WING F

Plinth100%
Podiums (if any) 0%

Aryan One Wing F

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

ARYAN ONE WING F

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Aryan One Wing F

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

ARYAN ONE WING F

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Aryan One Wing F

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 20%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.