AV Greenairy

by Falaqnuma Realty LLP Limited Liability Partnership
Certificate SignedPM1240002502574
AV GreenairyProject photos will appear here when available.

Project Information

RERA Certificate No.
PM1240002502574
Registration No.
PM1240002502574
Registration Date
2026-03-02
Developer
Falaqnuma Realty LLP Limited Liability Partnership
Proposed Possession
2030-04-30
Revised Possession
2029-12-31
Total Units
236
Units Sold
113 (48%)
Buildings
4
Project Area
11076.33 sq.m
MahaRERA QR
AV Greenairy
MahaRERA โ€” PM1240002502574
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable8
๐Ÿ”ขTotal Units52
๐ŸกResidential44
๐ŸขNon-Residential8
๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable8
๐Ÿ”ขTotal Units52
๐ŸกResidential44
๐ŸขNon-Residential8
๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable8
๐Ÿ”ขTotal Units69
๐ŸกResidential69
๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable8
๐Ÿ”ขTotal Units63
๐ŸกResidential63

Construction Progress

AV Greenairy Building A - Wing A

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

AV Greenairy Building B - Wing B

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

AV Greenairy Building C - Wing C

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

AV Greenairy Building D - Wing D

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โœ…Energy managemcnt
โœ…Fire protection and fire safety requirements
โฌœInternal Roads & Footpaths
โœ…Landscaping & Tree Planting
โœ…Open Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โœ…Solid Waste Management And Disposal
โœ…Storm Water Drains
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news โ†’
CallWhatsApp
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now