List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Chanewala Complex

by Rachana Developers Partnership
Certificate SignedPM1270002500060
Chanewala ComplexProject photos will appear here when available.

Project Information

RERA Certificate No.
PM1270002500060
Registration No.
ACK06052500083
Registration Date
2025-06-02
Developer
Rachana Developers Partnership
Architect
Sai
Project Bank
IDBI BANK
Proposed Possession
2030-04-30
Total Units
70
Units Sold
22 (31%)
Buildings
2
Project Area
1160.00 sq.m
Total FSI
3899.40
Approved FSI
3899.40
MahaRERA QR
Chanewala Complex
MahaRERA โ€” PM1270002500060
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable7
๐Ÿ”ขTotal Units62
๐ŸกResidential30
๐ŸขNon-Residential32
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ Habitable4
๐Ÿ”ขTotal Units8
๐ŸกResidential8

Construction Progress

A Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor0%

B Wing

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor0%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โฌœEnergy managemcnt
โœ…Fire protection and fire safety requirements
โœ…Internal Roads & Footpaths60%
โฌœLandscaping & Tree Planting
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)20%
โœ…Solid Waste Management And Disposal
โœ…Storm Water Drains
โœ…Street Lighting
โœ…Treatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply20%
โœ…Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news โ†’
CallWhatsApp
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now