Charms Hill

by M/S Prime Developers Partnership
Certificate SignedP51700007816
Charms HillProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700007816
Registration No.
REA51700019515
Registration Date
2017-08-18
Developer
M/S Prime Developers Partnership
Architect
Space Designers
Project Bank
UNION BANK OF INDIA
Proposed Possession
2019-12-31
Revised Possession
2018-12-31
Extended Possession
2019-12-31
Units Sold
0
Buildings
8
Project Area
3300.00 sq.m
Total FSI
3300.00
Approved FSI
3300.00
MahaRERA QR
Charms Hill
MahaRERA โ€” P51700007816
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors4
โœ…Sanctioned4
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ—๏ธProposed Floors4
โœ…Sanctioned4
๐Ÿ—๏ธProposed Floors4
โœ…Sanctioned4
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3

Apartment Configurations

B WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.9660
100%
1RK21.62660
100%

C WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.9660
100%
1RK21.62660
100%

D WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.6660
100%
1RK21.62660
100%

E WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.910100
100%
1BHK PLUS TERRACE29.9220
100%
SHOP11.61110
100%
SHOP13.08110
100%
SHOP17.24110
100%
SHOP18.43110
100%

F WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.912120
100%

G WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.912120
100%

H WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.612120
100%

Construction Progress

A WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

B WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

C WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

D WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

E WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

F WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

G WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

H WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station100%
โฌœEnergy managemcnt
โฌœFire protection and fire safety requirements
โฌœInternal Roads & Footpaths
โฌœLandscaping & Tree Planting
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
โฌœSolid Waste Management And Disposal
โฌœStorm Water Drains
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply100%
โฌœWater conservation /Rain water harvesting

Latest Mumbai Property News

View all news โ†’
CallWhatsApp
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now