List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Daisy Gardens Survey No 12 Phase Ii

by Ankita Builders Partnership
Certificate SignedP51700009095
Daisy Gardens Survey No 12 Phase IiProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700009095
Registration No.
REA51700017889
Registration Date
2017-08-19
Developer
Ankita Builders Partnership
Architect
Vitan Consultants
Project Bank
THE KALYAN JANATA SAHAKARI BANK LTD.
Proposed Possession
2018-07-30
Revised Possession
2018-07-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
8
Project Area
13340.00 sq.m
Total FSI
12041.49
Approved FSI
12041.49
MahaRERA QR
Daisy Gardens Survey No 12 Phase Ii
MahaRERA โ€” P51700009095
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors9
โœ…Sanctioned9
๐Ÿ—๏ธProposed Floors9
โœ…Sanctioned9
๐Ÿ—๏ธProposed Floors9
โœ…Sanctioned9
๐Ÿ—๏ธProposed Floors9
โœ…Sanctioned9
๐Ÿ—๏ธProposed Floors9
โœ…Sanctioned9
๐Ÿ—๏ธProposed Floors9
โœ…Sanctioned9
๐Ÿ—๏ธProposed Floors9
โœ…Sanctioned9
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3

Apartment Configurations

BUILDING NO 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.3928271
96%
SHOP13.25211
50%
SHOP16.26202
0%
SHOP18.33202
0%
SHOP20.34202
0%

BUILDING NO 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.7914113
79%
2 BHK48.241486
57%
2 BHK52.5514122
86%
SHOP12.93101
0%
SHOP14.58101
0%
SHOP16.17101
0%
SHOP16.57101
0%
SHOP19.88101
0%
SHOP21.64101
0%
SHOP22.39101
0%
SHOP24.75101
0%

BUILDING NO 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK44.2414014
0%
2 BHK47.791468
43%
2 BHK52.5514131
93%
SHOP12.93110
100%
SHOP14.58101
0%
SHOP16.17101
0%
SHOP16.57110
100%
SHOP19.88110
100%
SHOP21.64110
100%
SHOP22.39101
0%
SHOP24.75110
100%

BUILDING NO 6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.83281018
36%

BUILDING NO 7

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.98202
0%
1 BHK38.4428262
93%

BUILDING NO 8

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.98202
0%
1 BHK38.4428271
96%

BUILDING NO 9

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.98202
0%
1 BHK38.4428271
96%

ROW HOUSES

TypeCarpet (sq.ft)TotalBookedAvailableStatus
ROW HOUSE77.91725
29%

Construction Progress

BUILDING NO 1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 6

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 7

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 8

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 9

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

ROW HOUSES

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space100%
โœ…Community Buildings100%
โœ…Electrical meter room, sub-station, receiving station100%
โœ…Energy managemcnt100%
โœ…Fire protection and fire safety requirements100%
โœ…Internal Roads & Footpaths100%
โœ…Landscaping & Tree Planting100%
โœ…Open Parking100%
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
โœ…Solid Waste Management And Disposal100%
โœ…Storm Water Drains100%
โœ…Street Lighting100%
โœ…Treatment And Disposal Of Sewage And Sullage Water100%
โœ…Water Supply100%
โœ…Water conservation /Rain water harvesting100%