Project Information

RERA Certificate No.
P52000050588
Registration No.
REA52000133452
Registration Date
2023-04-21
Developer
UNICORP REALTY PRIVATE LIMITED Company
Project Bank
STATE BANK OF INDIA
Proposed Possession
2024-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
7
Project Area
4395.00 sq.m
Total FSI
6449.16
Approved FSI
6449.16
MahaRERA QR
Excellensea Villas Project
MahaRERA โ€” P52000050588
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ Habitable5
โฌ‡๏ธBasements1
๐Ÿ“…Completion2024-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ Habitable5
โฌ‡๏ธBasements1
๐Ÿ“…Completion2024-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ Habitable5
โฌ‡๏ธBasements1
๐Ÿ“…Completion2024-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ Habitable5
โฌ‡๏ธBasements1
๐Ÿ“…Completion2024-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ Habitable5
โฌ‡๏ธBasements1
๐Ÿ“…Completion2024-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ Habitable5
โฌ‡๏ธBasements1
๐Ÿ“…Completion2024-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ Habitable5
โฌ‡๏ธBasements1
๐Ÿ“…Completion2024-12-30

Apartment Configurations

Villa 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Villa653.15101
0%

Villa 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Villa653.15110
100%

Villa 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Villa653.15110
100%

Villa 4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Villa653.15110
100%

Villa 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Villa653.15110
100%

Villa 6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Villa653.15110
100%

Villa 7

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Villa653.15101
0%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Villa653.1500244140625000
0%

Construction Progress

Villa 1

Basement (if any)75%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth75%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

Villa 2

Basement (if any)75%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth75%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

Villa 3

Basement (if any)75%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth75%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

Villa 4

Basement (if any)75%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth75%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

Villa 5

Basement (if any)75%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth75%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

Villa 6

Basement (if any)75%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth75%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

Villa 7

Basement (if any)75%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth75%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical Meter Room Sub station and Internal Road street lighting
โฌœElectrical Meter Room, Sub-Station, Receiving Station
โฌœEnergy management
โฌœFire Protection And Fire Safety Requirements
โฌœLandscaping & Tree Planting
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โœ…Single water line tapping
โฌœSolid Waste Management And Disposal
โœ…Storm Water Drains
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โฌœWater Conservation, Rain water Harvesting
โฌœWater Supply
CallWhatsApp
โœ‰๏ธ

Get in Touch

Our team will connect with you shortly

+91
๐Ÿ”’ Your details are secure with us
โšก If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now