List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Gayatri Complex

by Kanubhai Mohanbhai Lakkad Individual
Certificate SignedP51700009950
Gayatri ComplexProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700009950
Registration No.
REA51700012950
Registration Date
2017-08-23
Developer
Kanubhai Mohanbhai Lakkad Individual
Architect
Rp Asundaria
Proposed Possession
2024-08-19
Revised Possession
2019-12-31
Extended Possession
2024-08-19
Units Sold
0
Buildings
5
Project Area
2600.00 sq.m
Total FSI
2210.00
Approved FSI
2210.00
MahaRERA QR
Gayatri Complex
MahaRERA โ€” P51700009950
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors1
โœ…Sanctioned1
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ—๏ธProposed Floors6
โœ…Sanctioned6
๐Ÿ—๏ธProposed Floors7
โœ…Sanctioned7
๐Ÿ—๏ธProposed Floors6
โœ…Sanctioned6

Apartment Configurations

Building No 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Shop11.61110
100%
Shop13.38110
100%
Shop14.3110
100%

Building No 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK25.08110
100%
1BHK42.271073
70%
1BHK52.57110
100%

Building No 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK25.08220
100%
1BHK26.29220
100%
1BHK31.5101
0%
1BHK34.43202
0%
1BHK34.46101
0%
1BHK34.56101
0%
1BHK34.57220
100%
1BHK34.6330
100%
1BHK34.67330
100%

Building No 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK34.03202
0%
1BHK37.9321
67%
1BHK38.4612012
0%
1BHK42.0110
100%
1BHK42.9303
0%

Building No4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK34.4412111
8%
1BHK34.51303
0%
1BHK37.58220
100%
1BHK39.94110
100%

Construction Progress

Building No 1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

Building No 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

Building No 3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

Building No 5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
Stilt Floor0%

Building No4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
Stilt Floor100%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station20%
โฌœEnergy managemcnt
โœ…Fire protection and fire safety requirements
โฌœInternal Roads & Footpaths
โฌœLandscaping & Tree Planting
โœ…Open Parking100%
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
โฌœSolid Waste Management And Disposal
โœ…Storm Water Drains100%
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting100%