Project Information

RERA Certificate No.
PM1240002502250
Developer
Mehta Ventures
Proposed Possession
2031-04-30
Total Units
572
Units Sold
7 (1%)
Buildings
4
MahaRERA QR
GOKUL HARI ANANTA
MahaRERA โ€” PM1240002502250
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors32
โœ…Sanctioned32
๐Ÿ Habitable29
๐Ÿ”ขTotal Units113
๐ŸกResidential108
๐ŸขNon-Residential5
๐Ÿ—๏ธProposed Floors32
โœ…Sanctioned32
๐Ÿ Habitable29
๐Ÿ”ขTotal Units169
๐ŸกResidential162
๐ŸขNon-Residential7
๐Ÿ—๏ธProposed Floors32
โœ…Sanctioned32
๐Ÿ Habitable29
๐Ÿ”ขTotal Units173
๐ŸกResidential162
๐ŸขNon-Residential11
๐Ÿ—๏ธProposed Floors32
โœ…Sanctioned32
๐Ÿ Habitable28
๐Ÿ”ขTotal Units117
๐ŸกResidential108
๐ŸขNon-Residential9

Construction Progress

Building No 1 - A

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)50%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure12%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
Stilt Floor50%

Building No 1 - B

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)37%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure9%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
Stilt Floor50%

Building No 1 - C

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)37%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure9%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
Stilt Floor50%

Building No 1 - D

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)25%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure6%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
Stilt Floor50%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โฌœEnergy managemcnt
โœ…Fire protection and fire safety requirements
โœ…Internal Roads & Footpaths
โœ…Landscaping & Tree Planting
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)40%
โœ…Solid Waste Management And Disposal
โœ…Storm Water Drains
โœ…Street Lighting
โœ…Treatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting