📞 +91 98200 30685 ✉️
RERA: A51800043517

Hari Krupa Residency, Kharde, Shahapur

by Harikrupa Buildcon Llp
Kept in Abeyance P51700010244
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700010244
Registration No.
REA51700019454
Developer
Harikrupa Buildcon Llp
Project Bank
Sarswat Bank
Proposed Possession
2022-07-31
Revised Possession
2023-07-31
Extended Possession
1900-01-01
Buildings
3
Project Area
2514.00 sq.m
Total FSI
2674.19
MahaRERA QR
Hari Krupa Residency, Kharde, Shahapur
MahaRERA — P51700010244
Scan to verify on MahaRERA portal

Wing-wise Details

🚗Open Parking9
🅿️Closed Parking3
📅Completion2022-07-31
🚗Open Parking9
🅿️Closed Parking3
📅Completion2022-07-31
📅Completion2022-07-31

Apartment Configurations

A Type Building Wing-A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 34.2 5 0 5
0%
1 BHK 34.73 1 0 1
0%
1 BHK 35.86 8 0 8
0%
2 BHK 38.74 4 3 1
75%
Shop 15.05 1 1 0
100%
SHOP1 15.05 1 0 1
0%
SHOP2 13.01 1 0 1
0%
SHOP3 14.31 1 1 0
100%
SHOP4 8.45 1 0 1
0%
SHOP5 14.31 1 0 1
0%
SHOP6 13.01 1 0 1
0%

A Type Building Wing-B

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 20.09 8 0 8
0%
1 BHK 23.21 1 0 1
0%
1 BHK 25.85 5 0 5
0%
1 BHK 26.49 4 0 4
0%
1 BHK 26.53 4 0 4
0%
1 BHK 32.71 8 0 8
0%
1 BHK 35.83 1 0 1
0%
1RK 17.24 5 0 5
0%
1RK 17.5 5 0 5
0%
1RK 19.42 4 0 4
0%
SHOP1 14.43 1 0 1
0%
SHOP2 12.43 1 0 1
0%
SHOP3 15.04 5 0 5
0%
SHOP4 12.95 2 0 2
0%
SHOP5 10.26 1 0 1
0%
SHOP6 12.57 2 0 2
0%
SHOP7 9.16 1 0 1
0%

D Type Wing -C

Type Carpet (sq.ft) Total Booked Available Status
NIL 0 0 0
0%

Construction Progress

A Type Building Wing-A

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

A Type Building Wing-B

Excavation0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

D Type Wing -C

Excavation0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting 40%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 40%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.