HORIZON PALMS II

by K M DEVELOPERS Partnership
Certificate Signed P51700011148
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700011148
Registration No.
REA51700016071
Registration Date
2021-09-09
Developer
K M DEVELOPERS Partnership
Architect
Architect Yogesh N Kelkar & Associates
Project Bank
DCB BANK LIMITED
Proposed Possession
2022-04-30
Revised Possession
2022-04-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
1353.18 sq.m
Total FSI
2192.15
Approved FSI
1707.73
MahaRERA QR
HORIZON PALMS II
MahaRERA — P51700011148
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🚗Open Parking6
🅿️Closed Parking9
📅Completion2021-04-30
🏗️Proposed Floors9
Sanctioned9
🚗Open Parking6
🅿️Closed Parking10
📅Completion2021-04-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1 Bhk Type A 38.22999954223633 0 0 0
0%
1 Bhk Type A 38.349998474121094 0 0 0
0%
1 Bhk Type C 37.29999923706055 0 0 0
0%
1 Bhk Type C 37.619998931884766 0 0 0
0%
1.5 Bhk Type B 34.97999954223633 0 0 0
0%
1.5 Bhk Type B 41.79999923706055 0 0 0
0%
2Bhk Type D 46.83000183105469 0 0 0
0%

A Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK TYPE A 38.35 7 6 1
86%
1 BHK TYPE C 37.62 7 7 0
100%
1.5 BHK TYPE B 41.8 7 7 0
100%

B Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK TYPE A 38.23 7 7 0
100%
1 BHK TYPE C 37.3 7 5 2
71%
1.5 BHK TYPE B 34.98 7 7 0
100%
2 BHK TYPE D 46.83 7 5 2
71%

Construction Progress

A WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.89%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises89%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
Stilt Floor 100%

B WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.89%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises89%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 95%
Energy management 100%
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 100%
Water Supply 85%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.