RERA: A51800043517

JAI SANTOSHI MATA HEIGHTS

by RAJIV THAKUR & ASSOCIATES Partnership
Certificate Signed P51700012270
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700012270
Registration No.
REA51700017711
Registration Date
2017-09-01
Developer
RAJIV THAKUR & ASSOCIATES Partnership
Architect
Pradeep M Kamble
Project Bank
DOMBIVLI NAGARI SAHAKARI BANK LIMITED
Proposed Possession
2018-03-31
Revised Possession
2018-03-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
1100.00 sq.m
Total FSI
1098.96
Approved FSI
1098.96
MahaRERA QR
JAI SANTOSHI MATA HEIGHTS
MahaRERA — P51700012270
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors7
Sanctioned7
🅿️Closed Parking1
📅Completion2018-03-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
Residential 1098.3599853515625 0 0 0
0%

Jai Santoshi Mata Heights

Type Carpet (sq.ft) Total Booked Available Status
RESIDENTIAL 1098.36 25 0 25
0%

Construction Progress

JAI SANTOSHI MATA HEIGHTS

Basement (if any)100%

Jai Santoshi Mata Heights

Excavation100%

JAI SANTOSHI MATA HEIGHTS

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%

Jai Santoshi Mata Heights

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%

JAI SANTOSHI MATA HEIGHTS

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%

Jai Santoshi Mata Heights

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80%
Overall Percentage of Completion of the work done For the entire Building /Wing75%

JAI SANTOSHI MATA HEIGHTS

Plinth100%
Podiums (if any) 0%

Jai Santoshi Mata Heights

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises80%

JAI SANTOSHI MATA HEIGHTS

Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%

Jai Santoshi Mata Heights

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%

JAI SANTOSHI MATA HEIGHTS

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%

Jai Santoshi Mata Heights

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing80%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure80%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 50%
Energy management
Fire Protection And Fire Safety Requirements 50%
Landscaping & Tree Planting
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 80%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water 80%
Water Conservation, Rain water Harvesting 100%
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.