Kalika Heights Phase II
by Sanjay shreenath pandey
Individual
Project Information
RERA Certificate No.
P51700011655
Registration No.
REA51700015079
Registration Date
2017-08-31
Developer
Sanjay shreenath pandey Individual
Project Bank
ICICI BANK LIMITED
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
2023-09-30
Units Sold
0
Buildings
2
Project Area
8839.29 sq.m
Kalika Heights Phase II
MahaRERA — P51700011655
MahaRERA — P51700011655
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors23
✅Sanctioned23
🚗Open
Parking9
🅿️Closed Parking7
📅Completion2022-09-30
🏗️Proposed Floors23
✅Sanctioned23
🚗Open
Parking9
🅿️Closed Parking6
📅Completion2022-09-30
Apartment Configurations
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1Bhk | 38.849998474121094 | 0 | 0 | 0 | 0% |
| 2Bhk | 57.34000015258789 | 0 | 0 | 0 | 0% |
| 2Bhk | 62.45000076293945 | 0 | 0 | 0 | 0% |
| 2Bhk | 75.73999786376953 | 0 | 0 | 0 | 0% |
| 2Bhk | 82.9000015258789 | 0 | 0 | 0 | 0% |
Kalika Heights Phase Ii A1 Wing
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 38.85 | 1 | 0 | 1 | 0% |
| 2 BHK | 57.34 | 6 | 2 | 4 | 33% |
| 2 BHK | 62.45 | 7 | 2 | 5 | 29% |
| 2 BHK | 75.74 | 7 | 3 | 4 | 43% |
| 2 BHK | 82.9 | 7 | 4 | 3 | 57% |
Kalika Heights Phase Ii Wing A2
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 38.85 | 1 | 0 | 1 | 0% |
| 2 BHK | 57.34 | 6 | 1 | 5 | 17% |
| 2 BHK | 62.45 | 7 | 3 | 4 | 43% |
| 2 BHK | 75.74 | 7 | 4 | 3 | 57% |
| 2 BHK | 82.9 | 7 | 2 | 5 | 29% |
Construction Progress
Kalika Heights Phase II A1 wing
Kalika Heights Phase II Wing A2
RERA Registered Amenities
✅
Aggregate area of recreational Open Space
⬜
Community Buildings
✅
Electrical Meter Room, Sub-Station, Receiving Station
50%
✅
Energy management
✅
Fire Protection And Fire Safety
Requirements
70%
✅
Landscaping & Tree Planting
✅
Open Parking
50%
✅
Sewerage (Chamber, Lines, Septic Tank , STP)
40%
✅
Solid Waste Management And Disposal
✅
Storm Water Drains
50%
⬜
Street Lighting
✅
Treatment And Disposal Of Sewage And Sullage Water
✅
Water Conservation, Rain water Harvesting
✅
Water Supply
50%