Milan Aura

by Milan Interbuilt Private Limited Company
Certificate SignedPR1180002500314
Milan AuraProject photos will appear here when available.

Project Information

RERA Certificate No.
PR1180002500314
Registration No.
ACK30052500857
Registration Date
2025-07-21
Developer
Milan Interbuilt Private Limited Company
Project Bank
AU SMALL FINANCE BANK LIMITED
Proposed Possession
2028-04-30
Total Units
38
Units Sold
3 (8%)
Buildings
1
Project Area
1357.66 sq.m
Total FSI
3242.69
Approved FSI
3242.69
MahaRERA QR
Milan Aura
MahaRERA โ€” PR1180002500314
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors10
โœ…Sanctioned10
๐Ÿ Habitable9
๐Ÿ”ขTotal Units24
๐ŸกResidential24
๐Ÿ—๏ธProposed Floors10
โœ…Sanctioned9
๐Ÿ Habitable8
๐Ÿ”ขTotal Units14
๐ŸกResidential14

Construction Progress

milan aura - WING-A

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure27%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks21%
Stilt Floor90%

milan aura - WING-B

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure27%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks21%
Stilt Floor90%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โฌœEnergy managemcnt
โœ…Fire protection and fire safety requirements
โฌœInternal Roads & Footpaths
โœ…Landscaping & Tree Planting
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โœ…Solid Waste Management And Disposal
โœ…Storm Water Drains
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting