Musavvir Residency

by Crystal Developers
Certificate SignedPM1240002500499
Musavvir ResidencyProject photos will appear here when available.

Project Information

RERA Certificate No.
PM1240002500499
Developer
Crystal Developers
Proposed Possession
2030-12-31
Total Units
104
Units Sold
14 (13%)
Buildings
1
MahaRERA QR
Musavvir Residency
MahaRERA โ€” PM1240002500499
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors7
โœ…Sanctioned7
๐Ÿ Habitable7
๐Ÿ”ขTotal Units54
๐ŸกResidential51
๐ŸขNon-Residential3
๐Ÿ—๏ธProposed Floors7
โœ…Sanctioned7
๐Ÿ Habitable7
๐Ÿ”ขTotal Units50
๐ŸกResidential50

Construction Progress

AB(New Jasmeen CHSL) - Wing A

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

AB(New Jasmeen CHSL) - Wing B

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โฌœEnergy managemcnt
โฌœFire protection and fire safety requirements
โœ…Internal Roads & Footpaths
โœ…Landscaping & Tree Planting
โœ…Open Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โœ…Solid Waste Management And Disposal
โœ…Storm Water Drains
โœ…Street Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news โ†’
CallWhatsApp
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now