RERA: A51800043517

NANA PATIL PRIDE

by PATIL BUILDERS AND DEVELOPERS Partnership
Certificate Signed P51700008376
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700008376
Registration No.
REA51700017959
Registration Date
2017-08-18
Developer
PATIL BUILDERS AND DEVELOPERS Partnership
Architect
Samarth Associates
Project Bank
BANK OF INDIA
Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
2019-12-31
Units Sold
0
Buildings
10
Project Area
17323.40 sq.m
Total FSI
17553.06
Approved FSI
14854.12
MahaRERA QR
NANA PATIL PRIDE
MahaRERA — P51700008376
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors14
Sanctioned14
⬇️Basements1
🚗Open Parking20
📅Completion2018-12-31
🏗️Proposed Floors14
Sanctioned14
⬇️Basements1
🚗Open Parking20
📅Completion2018-12-31
🏗️Proposed Floors3
Sanctioned3
🚗Open Parking1
📅Completion2018-12-31
🏗️Proposed Floors3
Sanctioned3
🚗Open Parking1
📅Completion2018-12-31
🏗️Proposed Floors3
Sanctioned3
🚗Open Parking1
📅Completion2018-12-31
🏗️Proposed Floors8
Sanctioned8
⬇️Basements1
🚗Open Parking10
📅Completion2018-12-31
🏗️Proposed Floors14
Sanctioned14
⬇️Basements1
🚗Open Parking36
📅Completion2018-12-31
🏗️Proposed Floors8
Sanctioned8
🚗Open Parking12
📅Completion2018-12-31
🏗️Proposed Floors8
Sanctioned8
🚗Open Parking10
📅Completion2018-12-31
🏗️Proposed Floors5
Sanctioned5
⬇️Basements1
🚗Open Parking8
📅Completion2018-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1 Bhk 31.510000228881836 0 0 0
0%
1 Bhk 32.06999969482422 0 0 0
0%
1Bhk 31.360000610351562 0 0 0
0%
1Bhk 31.510000228881836 0 0 0
0%
1Bhk 31.770000457763672 0 0 0
0%
1Bhk 31.90999984741211 0 0 0
0%
1Bhk 31.920000076293945 0 0 0
0%
1Bhk 32.06999969482422 0 0 0
0%
1Bhk 32.18000030517578 0 0 0
0%
1Bhk 32.34000015258789 0 0 0
0%
1Bhk 32.630001068115234 0 0 0
0%
1Bhk 33.08000183105469 0 0 0
0%
1Rk 23.360000610351562 0 0 0
0%
1Rk 23.510000228881836 0 0 0
0%
1Rk 24.600000381469727 0 0 0
0%
2 Bhk Duplex 75.55999755859375 0 0 0
0%
2Bhk 46.86000061035156 0 0 0
0%
2Bhk 46.88999938964844 0 0 0
0%
2Bhk 46.900001525878906 0 0 0
0%
2Bhk 47.0 0 0 0
0%
2Bhk 47.02000045776367 0 0 0
0%
2Bhk 47.06999969482422 0 0 0
0%
2Bhk 47.58000183105469 0 0 0
0%
2Bhk 47.61000061035156 0 0 0
0%
2Bhk 47.77000045776367 0 0 0
0%
2Bhk 47.779998779296875 0 0 0
0%
2Bhk 48.20000076293945 0 0 0
0%
2Bhk 49.06999969482422 0 0 0
0%
2Bhk 49.47999954223633 0 0 0
0%
2Bhk 50.5 0 0 0
0%
2Bhk 51.099998474121094 0 0 0
0%
2Bhk Duplex 77.27999877929688 0 0 0
0%
3Bhk 63.0 0 0 0
0%
3Bhk 63.189998626708984 0 0 0
0%
3Bhk 63.29999923706055 0 0 0
0%
3Bhk 63.59000015258789 0 0 0
0%
3Bhk 64.3499984741211 0 0 0
0%
3Bhk 64.83999633789062 0 0 0
0%
Basement 135.85000610351562 0 0 0
0%
Commercial 135.85000610351562 0 0 0
0%
Commertial 135.52999877929688 0 0 0
0%
Row House 95.41000366210938 0 0 0
0%
Shop 11.369999885559082 0 0 0
0%
Shop 11.579999923706055 0 0 0
0%
Shop 11.800000190734863 0 0 0
0%
Shop 11.949999809265137 0 0 0
0%
Shop 11.960000038146973 0 0 0
0%
Shop 12.0 0 0 0
0%
Shop 14.359999656677246 0 0 0
0%
Shop 14.390000343322754 0 0 0
0%
Shop 14.529999732971191 0 0 0
0%
Shop 14.710000038146973 0 0 0
0%
Shop 15.3100004196167 0 0 0
0%
Shop 15.579999923706055 0 0 0
0%
Shop 16.489999771118164 0 0 0
0%
Shop 16.770000457763672 0 0 0
0%
Shop 23.149999618530273 0 0 0
0%
Shop 27.149999618530273 0 0 0
0%

Building 2 B-Wing

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 47.0 1 0 1
0%
2 BHK 47.02 1 0 1
0%
2 BHK 47.07 23 5 18
22%
2 BHK 47.78 23 16 7
70%
2 BHK DUPLEX 77.28 1 0 1
0%
SHOP 12.0 2 1 1
50%
SHOP 14.36 1 1 0
100%
SHOP 14.53 1 1 0
100%
SHOP 15.31 2 2 0
100%
SHOP 16.49 2 2 0
100%

Building 2 C-Wing

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 47.0 2 0 2
0%
2 BHK 47.07 23 4 19
17%
2 BHK 47.58 1 1 0
100%
2 BHK 47.77 10 7 3
70%
2 BHK 47.78 12 10 2
83%
2 BHK DUPLEX 75.56 1 0 1
0%
SHOP 12.0 2 2 0
100%
SHOP 14.53 1 1 0
100%
SHOP 14.71 1 1 0
100%
SHOP 15.31 2 2 0
100%
SHOP 16.49 2 2 0
100%

Building 5 Row House 1

Type Carpet (sq.ft) Total Booked Available Status
ROW HOUSE 95.41 1 0 1
0%

Building 5 Row House 2

Type Carpet (sq.ft) Total Booked Available Status
ROW HOUSE 95.41 3 0 3
0%

Building 5 Row House 3

Type Carpet (sq.ft) Total Booked Available Status
ROW HOUSE 95.41 3 0 3
0%

Building-2 D-Wing

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 46.86 1 0 1
0%
2 BHK 46.89 6 3 3
50%
2 BHK 46.9 6 0 6
0%
2 BHK 47.61 12 9 3
75%
2 BHK 48.2 6 5 1
83%
2 BHK 49.07 6 5 1
83%
2 BHK 49.48 6 1 5
17%
2 BHK 50.5 6 5 1
83%
2 BHK 51.1 1 0 1
0%
3 BHK 63.0 1 0 1
0%
3 BHK 63.19 6 6 0
100%
3 BHK 63.3 1 0 1
0%
3 BHK 63.59 6 5 1
83%
3 BHK 64.35 6 4 2
67%
3 BHK 64.84 6 5 1
83%
SHOP 12.0 2 2 0
100%
SHOP 14.36 1 1 0
100%
SHOP 15.31 1 1 0
100%
SHOP 15.58 1 1 0
100%
SHOP 16.49 1 1 0
100%
SHOP 16.77 1 1 0
100%
SHOP 23.15 1 1 0
100%
SHOP 27.15 1 0 1
0%

Building-3 E-Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 31.36 4 2 2
50%
1 BHK 31.51 6 3 3
50%
1 BHK 31.77 1 0 1
0%
1 BHK 31.91 6 6 0
100%
1 BHK 31.92 1 0 1
0%
1 BHK 32.07 4 3 1
75%
1 BHK 32.18 3 3 0
100%
1 BHK 32.34 3 2 1
67%
1 BHK 32.63 4 2 2
50%
1 BHK 33.08 4 4 0
100%
1RK 23.36 1 0 1
0%
1RK 24.6 1 0 1
0%
SHOP 11.37 2 2 0
100%
SHOP 11.8 1 0 1
0%
SHOP 11.95 2 1 1
50%
SHOP 14.39 2 2 0
100%

Building-3 F-Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 31.51 15 10 5
67%
1 BHK 32.07 14 11 3
79%
1RK 23.51 1 0 1
0%
SHOP 11.37 1 1 0
100%
SHOP 11.58 1 1 0
100%
SHOP 11.95 1 1 0
100%
SHOP 11.96 1 1 0
100%
SHOP 14.39 2 2 0
100%

Building-4 G-Wing

Type Carpet (sq.ft) Total Booked Available Status
BASEMENT 135.85 1 0 1
0%
COMMERCIAL 135.85 1 0 1
0%
COMMERTIAL 135.53 3 0 3
0%

Construction Progress

BUILDING 2 B-WING

Basement (if any)100%

Building 2 B-Wing

Excavation100%

BUILDING 2 B-WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%

Building 2 B-Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate60%

BUILDING 2 B-WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building 2 B-Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

BUILDING 2 B-WING

Plinth100%
Podiums (if any) 0%

Building 2 B-Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises80%

BUILDING 2 B-WING

Sanitary Fittings within the flats / premises80%
Slabs of Super Structure100%

Building 2 B-Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.98%

BUILDING 2 B-WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%

Building 2 B-Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING 2 C-WING

Basement (if any)100%

Building 2 C-Wing

Excavation100%

BUILDING 2 C-WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%

Building 2 C-Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate60%

BUILDING 2 C-WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%

Building 2 C-Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises96%

BUILDING 2 C-WING

Plinth100%
Podiums (if any) 0%

Building 2 C-Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises80%

BUILDING 2 C-WING

Sanitary Fittings within the flats / premises80%
Slabs of Super Structure100%

Building 2 C-Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.98%

BUILDING 2 C-WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%

Building 2 C-Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing98%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING 5 ROW HOUSE 1

Basement (if any)0%

Building 5 Row House 1

Excavation0%

BUILDING 5 ROW HOUSE 1

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building 5 Row House 1

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING 5 ROW HOUSE 1

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building 5 Row House 1

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

BUILDING 5 ROW HOUSE 1

Plinth0%
Podiums (if any) 0%

Building 5 Row House 1

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING 5 ROW HOUSE 1

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Building 5 Row House 1

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING 5 ROW HOUSE 1

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building 5 Row House 1

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUILDING 5 ROW HOUSE 2

Basement (if any)0%

Building 5 Row House 2

Excavation0%

BUILDING 5 ROW HOUSE 2

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building 5 Row House 2

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING 5 ROW HOUSE 2

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building 5 Row House 2

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

BUILDING 5 ROW HOUSE 2

Plinth0%
Podiums (if any) 0%

Building 5 Row House 2

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING 5 ROW HOUSE 2

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Building 5 Row House 2

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING 5 ROW HOUSE 2

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building 5 Row House 2

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUILDING 5 ROW HOUSE 3

Basement (if any)0%

Building 5 Row House 3

Excavation0%

BUILDING 5 ROW HOUSE 3

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building 5 Row House 3

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING 5 ROW HOUSE 3

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building 5 Row House 3

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

BUILDING 5 ROW HOUSE 3

Plinth0%
Podiums (if any) 0%

Building 5 Row House 3

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING 5 ROW HOUSE 3

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Building 5 Row House 3

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING 5 ROW HOUSE 3

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building 5 Row House 3

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUILDING-1 A-WING

Basement (if any)100%

Building-1 A-Wing

Excavation100%

BUILDING-1 A-WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%

Building-1 A-Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING-1 A-WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%

Building-1 A-Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60%
Overall Percentage of Completion of the work done For the entire Building /Wing64%

BUILDING-1 A-WING

Plinth100%
Podiums (if any) 0%

Building-1 A-Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING-1 A-WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Building-1 A-Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING-1 A-WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building-1 A-Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing80%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING-2 D-WING

Basement (if any)100%

Building-2 D-Wing

Excavation100%

BUILDING-2 D-WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%

Building-2 D-Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate60%

BUILDING-2 D-WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%

Building-2 D-Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises97%

BUILDING-2 D-WING

Plinth100%
Podiums (if any) 0%

Building-2 D-Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

BUILDING-2 D-WING

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%

Building-2 D-Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.97%

BUILDING-2 D-WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%

Building-2 D-Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing98%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING-3 E-WING

Basement (if any)100%

Building-3 E-Wing

Excavation100%

BUILDING-3 E-WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%

Building-3 E-Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate60%

BUILDING-3 E-WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%

Building-3 E-Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises99%

BUILDING-3 E-WING

Plinth100%
Podiums (if any) 0%

Building-3 E-Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

BUILDING-3 E-WING

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%

Building-3 E-Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING-3 E-WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building-3 E-Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing98%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING-3 F-WING

Basement (if any)100%

Building-3 F-Wing

Excavation100%

BUILDING-3 F-WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%

Building-3 F-Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate60%

BUILDING-3 F-WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%

Building-3 F-Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises97%

BUILDING-3 F-WING

Plinth100%
Podiums (if any) 0%

Building-3 F-Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

BUILDING-3 F-WING

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%

Building-3 F-Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING-3 F-WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building-3 F-Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing98%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING-4 G-WING

Basement (if any)100%

Building-4 G-Wing

Excavation100%

BUILDING-4 G-WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building-4 G-Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING-4 G-WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%

Building-4 G-Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70%
Overall Percentage of Completion of the work done For the entire Building /Wing42%

BUILDING-4 G-WING

Plinth100%
Podiums (if any) 0%

Building-4 G-Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING-4 G-WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Building-4 G-Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%

BUILDING-4 G-WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Building-4 G-Wing

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 40%
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting 80%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 80%
Solid Waste Management And Disposal
Storm Water Drains 80%
Street Lighting 50%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply 90%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.