📞 +91 98200 30685 ✉️
RERA: A51800043517

OM SHIV SAMARTH CHS

by SHREE SAIBABA CONSTRUCTIONS PRIVATE LIMITED Company
Certificate Signed P51700012275
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700012275
Registration No.
REA51700012549
Registration Date
2017-09-01
Developer
SHREE SAIBABA CONSTRUCTIONS PRIVATE LIMITED Company
Architect
Yogesh Kelkar
Project Bank
TJSB SAHAKARI BANK LTD
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
2022-08-31
Units Sold
0
Buildings
2
Project Area
2724.18 sq.m
Total FSI
8131.15
Approved FSI
6664.95
MahaRERA QR
OM SHIV SAMARTH CHS
MahaRERA — P51700012275
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors20
Sanctioned20
🅿️Closed Parking1
📅Completion1900-01-01
🏗️Proposed Floors29
Sanctioned29
🚗Open Parking65
🅿️Closed Parking1
📅Completion1900-01-01

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1 Bhk 26.010000228881836 0 0 0
0%
1 Bhk 26.049999237060547 0 0 0
0%
1 Bhk 26.1299991607666 0 0 0
0%
1 Bhk 38.75 0 0 0
0%
1 Bhk 43.0 0 0 0
0%
1 Bhk 49.0 0 0 0
0%
1 Bhk 49.5 0 0 0
0%
1 Rk 25.0 0 0 0
0%
2 Bhk 54.0 0 0 0
0%
2 Bhk 57.25 0 0 0
0%
2.5 Bhk 88.25 0 0 0
0%
Shop 1 21.40999984741211 0 0 0
0%
Shop 2 13.930000305175781 0 0 0
0%
Shop 3 16.309999465942383 0 0 0
0%
Shop 4 17.110000610351562 0 0 0
0%
Shop 5 25.309999465942383 0 0 0
0%
Shop 6 25.280000686645508 0 0 0
0%
Shop 7 25.350000381469727 0 0 0
0%

Om Shiv Samarth Chs

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 26.01 102 102 0
100%
1 BHK 26.05 17 17 0
100%
1 BHK 26.13 18 18 0
100%
SHOP 1 21.41 1 1 0
100%
SHOP 2 13.93 1 1 0
100%
SHOP 3 16.31 1 1 0
100%
SHOP 4 17.11 1 1 0
100%
SHOP 5 25.31 1 1 0
100%
SHOP 6 25.28 1 1 0
100%
SHOP 7 25.35 1 1 0
100%

Panchpakhadi Jewel

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 38.75 10 4 6
40%
1 BHK 43.0 1 1 0
100%
1 BHK 49.0 10 4 6
40%
1 BHK 49.5 1 0 1
0%
1 RK 25.0 3 2 1
67%
2 BHK 54.0 13 11 2
85%
2 BHK 57.25 15 10 5
67%
2.5 BHK 88.25 6 5 1
83%

Construction Progress

OM SHIV SAMARTH CHS

Basement (if any)100%

Om Shiv Samarth Chs

Excavation100%

OM SHIV SAMARTH CHS

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Om Shiv Samarth Chs

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

OM SHIV SAMARTH CHS

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Om Shiv Samarth Chs

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

OM SHIV SAMARTH CHS

Plinth100%
Podiums (if any) 0%

Om Shiv Samarth Chs

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

OM SHIV SAMARTH CHS

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Om Shiv Samarth Chs

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

OM SHIV SAMARTH CHS

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Om Shiv Samarth Chs

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

PANCHPAKHADI JEWEL

Basement (if any)100%

Panchpakhadi Jewel

Excavation100%

PANCHPAKHADI JEWEL

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%

Panchpakhadi Jewel

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate45%

PANCHPAKHADI JEWEL

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.45%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises86%

Panchpakhadi Jewel

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises86%

PANCHPAKHADI JEWEL

Plinth100%
Podiums (if any) 100%

Panchpakhadi Jewel

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises80%

PANCHPAKHADI JEWEL

Sanitary Fittings within the flats / premises80%
Slabs of Super Structure87%

Panchpakhadi Jewel

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.95%

PANCHPAKHADI JEWEL

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%

Panchpakhadi Jewel

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure87%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking 50%
OTHER
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.