Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
2023-12-30
Buildings
2
Project Area
2910.00 sq.m
Total FSI
3614.00
MahaRERA QR
Prime Balaji Height
MahaRERA — P51700010278
Scan to verify on MahaRERA portal

Wing-wise Details

🚗Open Parking15
🅿️Closed Parking1
📅Completion2021-06-30
🚗Open Parking8
🅿️Closed Parking1
📅Completion2021-06-30

Apartment Configurations

A Wing

Type Carpet (sq.ft) Total Booked Available Status
Commercial 32.88 1 0 1
0%
Residential 39.48 1 0 1
0%

B Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 21.12 8 7 1
88%
1 BHK 22.86 15 12 3
80%
1 BHK 24.23 8 6 2
75%
1 BHK 24.36 8 6 2
75%
1 BHK 26.09 10 9 1
90%
1 BHK 26.2 5 5 0
100%
1 BHK 31.05 1 1 0
100%
1 BHK 31.24 1 1 0
100%
1RK 14.37 18 14 4
78%
1RK 15.19 8 8 0
100%
Shop 5.92 2 2 0
100%
Shop 19.3 2 0 2
0%

Construction Progress

A Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

B Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate40%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70%
Overall Percentage of Completion of the work done For the entire Building /Wing65%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.60%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing40%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure90%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 80%
Energy management
Fire Protection And Fire Safety Requirements 75%
Landscaping & Tree Planting 95%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 95%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 80%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.