🏆 Mumbai's oldest property portalSince 1995✓ MahaRERA A51800043517✓ RERA-verified project data🟢 We reply in minutes on WhatsApp
P
✓ MahaRERA P99000054025✓ Clear

Pushpraj Industrial Park

📍 Vasai East, Palghar · 401208
114
Units
2026
Possession
2
Buildings
Certificate Signed
Status
01Possession Timeline
Proposed
Mar 2026
Status
New
02Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Second735 ft²On request
Third Flo735 ft²On request
Third984–1,144 ft²On request
Secon984–1,144 ft²On request
First735–1,144 ft²On request
Third Floor441–1,295 ft²On request
First Floor441–1,295 ft²On request
Second Floor441–1,295 ft²On request
Ground Floor611–2,313 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Live availability, floor plans & today's price — on WhatsApp
03RERA Trust Record
MahaRERA No.
P99000054025
Registered
2023-12-19
Litigation
None on record
Escrow Bank
HDFC BANK
Architect
Chirag Mistry And Associates
Total FSI
14153
04Buildings · 2 Wing(s)
Building No 23 floors · 43 units
Building No13 floors · 71 units
05Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06Location
📍 Vasai East
19.40890038696897,72.8790769231442
▸ Explore map & Street View — for verified buyers
07Promoter & Professionals
HURBEN BHIKABHAI HALAPartner
09Construction Progress52% avg
Basement (if any)100%
Excavation100%
Plinth100%
Stilt Floor100%
X number of Basement(s) and Plinth100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
Slabs of Super Structure75%
Overall Percentage of Completion of the work done For the entire Building /Wing30%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
10Amenities
Electrical Meter Room, Sub-Station, Receiving StationOTHERS COMPOUND WALLSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsStreet LightingWater Conservation, Rain water HarvestingWater Supply
12Floor Plans, E-Brochure & Payment Plans
📐 Unit floor plans📄 Official e-brochure💳 Payment plans · 20:80 · subvention · current offers

Shared on WhatsApp by our MahaRERA advisor — including the latest builder offers and payment schemes we don't list publicly.

💬 Get floor plan, brochure & offers on WhatsApp
13EMI Calculator
14More by S K Developers
Codename CoralMira Road · Under ConstructionKaustubh Park 91Borivali West · Under ConstructionSeasonsNaigaon East · Under ConstructionNotan HouseJuhu · Under ConstructionNotan EdgeVile Parle West · Under ConstructionNotan TidesJuhu · Under Construction
15MahaRERA projects nearby in Vasai East
OLYMPUS TOWERS355 unitsLAKE SUPERIOR157 unitsImperial Splendora - C and E Wing96 unitsImperial Indrapuram88 unitsSUNSHINE SAPPHIRERashmi Hill ViewNEELKANTH INDUSTRYJANAVI PLAZA, JANAVI TOWERRELIABLE UTKARSH A,B WINGManav ResidencyImperial PalmsVORA ASSOCIATES
?Frequently Asked Questions
When is possession of PUSHPRAJ INDUSTRIAL PARK?

As per MahaRERA, proposed possession is Mar 2026.

Is PUSHPRAJ INDUSTRIAL PARK RERA-registered?

Yes — MahaRERA registration P99000054025, registered 2023-12-19. No litigations on record.

Who is the developer?

S K Developers — 5903 projects tracked on Mumbai Property Exchange. View their track record ▸

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.

SOURCE · MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA · RERA A51800043517 · EST. 1995
WhatsAppEnquire ▸
🎯 AI Matchmaker
Tell us what you want in Vasai East — get matched
RERA-verified options on WhatsApp. No spam, no fakes.
✓ MahaRERA P51700077356★ Featured
Lodha Group
Lodha Hanging Gardens, Dombivali
3 BHK, 4 BHK · ₹16,400/sq.ft · Possession Dec 2027
Learn more ›

📰 Latest Mumbai Property News

View all news →