📞 +91 98200 30685 ✉️
RERA: A51800043517

Raj Torres Phase II Wing A Wing B Wing C Wing D Wing E

by RAJESH ESTATES AND NIRMAN PVT LTD Company
Certificate Signed P51700008352
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700008352
Registration No.
REA51700017034
Registration Date
2021-09-09
Developer
RAJESH ESTATES AND NIRMAN PVT LTD Company
Architect
Anil Jagwani
Project Bank
ICICI BANK LIMITED
Proposed Possession
2022-03-30
Revised Possession
2022-03-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
5
Project Area
2102.61 sq.m
Total FSI
49288.00
Approved FSI
30228.00
MahaRERA QR
Raj Torres Phase II Wing A Wing B Wing C Wing D Wing E
MahaRERA — P51700008352
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors35
Sanctioned35
⬇️Basements1
🅿️Closed Parking110
📅Completion2021-03-31
🏗️Proposed Floors35
Sanctioned35
⬇️Basements1
🅿️Closed Parking110
📅Completion2021-03-31
🏗️Proposed Floors35
Sanctioned35
⬇️Basements1
🅿️Closed Parking168
📅Completion2021-03-31
🏗️Proposed Floors34
Sanctioned34
⬇️Basements1
🅿️Closed Parking107
📅Completion2021-03-31
🏗️Proposed Floors34
Sanctioned34
⬇️Basements1
🅿️Closed Parking107
📅Completion2021-03-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2Bhk 67.20999908447266 0 0 0
0%
2Bhk 67.68000030517578 0 0 0
0%
2Bhk 67.81999969482422 0 0 0
0%
2Bhk 68.0 0 0 0
0%
2Bhk 68.08000183105469 0 0 0
0%
2Bhk 68.33999633789062 0 0 0
0%
2Bhk 68.58999633789062 0 0 0
0%
2Bhk 69.02999877929688 0 0 0
0%
3Bhk 88.9800033569336 0 0 0
0%
3Bhk 89.62000274658203 0 0 0
0%
3Bhk 89.6500015258789 0 0 0
0%
3Bhk 90.08000183105469 0 0 0
0%
3Bhk 95.91999816894531 0 0 0
0%
3Bhk 95.98999786376953 0 0 0
0%
3Bhk 96.19999694824219 0 0 0
0%
3Bhk 96.9000015258789 0 0 0
0%
3Bhk 96.93000030517578 0 0 0
0%
4Bhk 128.57000732421875 0 0 0
0%

Raj Torres Wing A

Type Carpet (sq.ft) Total Booked Available Status
3 BHK 88.98 29 11 18
38%
3 BHK 89.62 29 7 22
24%
3 BHK 95.99 29 5 24
17%
3 BHK 96.2 22 6 16
27%

Raj Torres Wing B

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 67.82 29 17 12
59%
2 BHK 68.0 29 16 13
55%
2 BHK 68.08 22 9 13
41%
2 BHK 68.34 29 19 10
66%

Raj Torres Wing C

Type Carpet (sq.ft) Total Booked Available Status
3 BHK 89.65 29 6 23
21%
3 BHK 90.08 29 15 14
52%
3 BHK 96.9 22 3 19
14%
3 BHK 96.93 29 25 4
86%
4 BHK 128.57 29 3 26
10%

Raj Torres Wing D

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 67.21 56 35 21
62%
2 BHK 67.68 50 33 17
66%

Raj Torres Wing E

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 68.59 22 7 15
32%
2 BHK 69.03 28 17 11
61%
3 BHK 95.92 56 16 40
29%

Construction Progress

Raj Torres Wing A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing33%
Plinth100%
Podiums (if any) 65%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor65%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums65%
X number of Slabs of Super Structure0%

Raj Torres Wing B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing31%
Plinth100%
Podiums (if any) 55%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor55%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums55%
X number of Slabs of Super Structure0%

Raj Torres Wing C

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises15%
Plinth100%
Podiums (if any) 55%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure62%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor50%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums55%
X number of Slabs of Super Structure62%

RAj Torres Wing D

Basement (if any)100%

Raj Torres Wing D

Excavation100%

RAj Torres Wing D

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Raj Torres Wing D

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

RAj Torres Wing D

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Raj Torres Wing D

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%

RAj Torres Wing D

Plinth100%
Podiums (if any) 55%

Raj Torres Wing D

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

RAj Torres Wing D

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure62%

Raj Torres Wing D

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

RAj Torres Wing D

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Raj Torres Wing D

Stilt Floor50%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums55%
X number of Slabs of Super Structure62%

Raj Torres Wing E

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Plinth100%
Podiums (if any) 36%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure7%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
Stilt Floor40%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums36%
X number of Slabs of Super Structure7%

RERA Registered Amenities

Aggregate area of recreational Open Space
CLUB HOUSE AND ADDITIONAL FACILITIES
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.