List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Rameshwar Park - Daffodil A

by Rameshawar Builders & Developers Partnership
Certificate SignedP51700014029
Rameshwar Park - Daffodil AProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700014029
Registration No.
REA51700025477
Registration Date
2021-09-09
Developer
Rameshawar Builders & Developers Partnership
Architect
Sameer S Lotke And Associates
Project Bank
KARUR VYSYA BANK
Proposed Possession
2022-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
236.00 sq.m
Total FSI
2720.68
Approved FSI
2720.68
MahaRERA QR
Rameshwar Park - Daffodil A
MahaRERA โ€” P51700014029
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors16
โœ…Sanctioned16

Apartment Configurations

DAFFODIL - A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK35.95220
100%
1BHK36.1433330
100%

Construction Progress

DAFFODIL - A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor90%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โœ…Community Buildings90%
โœ…Electrical meter room, sub-station, receiving station100%
โœ…Energy managemcnt100%
โœ…Fire protection and fire safety requirements100%
โœ…Internal Roads & Footpaths90%
โœ…Landscaping & Tree Planting75%
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)75%
โฌœSolid Waste Management And Disposal
โœ…Storm Water Drains75%
โœ…Street Lighting100%
โœ…Treatment And Disposal Of Sewage And Sullage Water100%
โœ…Water Supply75%
โœ…Water conservation /Rain water harvesting90%