📞 +91 98200 30685 ✉️
RERA: A51800043517

RAMESHWAR PARK (ORCHID, IRIS & ROSE)

by RAMESHAWAR BUILDERS & DEVELOPERS Partnership
Certificate Signed P51700008168
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700008168
Registration No.
REA51700018783
Registration Date
2020-02-10
Developer
RAMESHAWAR BUILDERS & DEVELOPERS Partnership
Architect
Sameer S. Lotke & Associates
Project Bank
KARUR VYSYA BANK
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
5
Project Area
725.50 sq.m
Total FSI
14132.06
Approved FSI
7022.06
MahaRERA QR
RAMESHWAR PARK (ORCHID, IRIS & ROSE)
MahaRERA — P51700008168
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking1
📅Completion1900-01-01

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 28.239999771118164 0 0 0
0%
Residential 1 Bhk 28.239999771118164 0 0 0
0%
Residential 1 Bhk 29.639999389648438 0 0 0
0%
Residential 1 Bhk 44.5 0 0 0
0%
Residential 1 Bhk 46.08000183105469 0 0 0
0%
Residential 1 Bhk 47.099998474121094 0 0 0
0%

Iris-A

Type Carpet (sq.ft) Total Booked Available Status
RESIDENTIAL 1 BHK 29.64 28 28 0
100%

Iris-B

Type Carpet (sq.ft) Total Booked Available Status
RESIDENTIAL 1 BHK 29.64 28 24 4
86%

Orchid-A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 28.24 28 28 0
100%

Orchid-B

Type Carpet (sq.ft) Total Booked Available Status
RESIDENTIAL 1 BHK 28.24 28 28 0
100%

Rose-Mhada

Type Carpet (sq.ft) Total Booked Available Status
RESIDENTIAL 1 BHK 44.5 7 0 7
0%
RESIDENTIAL 1 BHK 46.08 7 0 7
0%
RESIDENTIAL 1 BHK 47.1 14 0 14
0%

Construction Progress

IRIS-A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

IRIS-B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

ORCHID-A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

ORCHID-B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

ROSE-MHADA

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings 90%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting 75%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 75%
Solid Waste Management And Disposal
Storm Water Drains 75%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 90%
Water Supply 75%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.