📞 +91 98200 30685 ✉️
RERA: A51800043517

ROYAL MEADOWS C 1 , C 2

by SIDDHIVINAYAK DEVELOPERS Partnership
Certificate Signed P51700008736
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700008736
Registration No.
REA51700018213
Registration Date
2017-08-19
Developer
SIDDHIVINAYAK DEVELOPERS Partnership
Architect
Architects Inc
Project Bank
THE KALYAN JANATA SAHAKARI BANK LTD.
Proposed Possession
2020-09-01
Revised Possession
2020-09-01
Extended Possession
2023-03-31
Total Units
188
Units Sold
179 (95%)
Buildings
2
Project Area
5589.33 sq.m
Total FSI
10219.79
Approved FSI
4553.23
MahaRERA QR
ROYAL MEADOWS C 1 , C 2
MahaRERA — P51700008736
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors18
Sanctioned18
🏠Habitable16
🔢Total Units94
🏡Residential94
🅿️Closed Parking38
📅Completion2020-01-09
🏗️Proposed Floors18
Sanctioned18
🏠Habitable16
🔢Total Units94
🏡Residential94
🅿️Closed Parking38
📅Completion2020-01-09

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 38.0099983215332 0 0 0
0%
1Bhk 38.060001373291016 0 0 0
0%
2Bhk 54.75 0 0 0
0%
2Bhk 56.439998626708984 0 0 0
0%
2Bhk 59.54999923706055 0 0 0
0%
3Bhk 77.11000061035156 0 0 0
0%

C - 2 Siddhi

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 38.01 14 3 11
21%
1 BHK 38.06 16 6 10
38%
2 BHK 54.75 16 6 10
38%
2 BHK 56.44 16 10 6
62%
2 BHK 59.55 16 10 6
62%
3 BHK 77.11 16 9 7
56%

C 1 - Riddhi

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 38.01 14 8 6
57%
1 BHK 38.06 16 5 11
31%
2 BHK 54.75 16 9 7
56%
2 BHK 56.44 16 9 7
56%
2 BHK 59.55 16 3 13
19%
3 BHK 77.11 16 11 5
69%

Construction Progress

C - 2 SIDDHI

Basement (if any)100%

C - 2 Siddhi

Excavation100%

C - 2 SIDDHI

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

C - 2 Siddhi

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80%

C - 2 SIDDHI

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

C - 2 Siddhi

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing98%

C - 2 SIDDHI

Plinth100%
Podiums (if any) 100%

C - 2 Siddhi

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

C - 2 SIDDHI

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

C - 2 Siddhi

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

C - 2 SIDDHI

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

C - 2 Siddhi

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

C 1 - RIDDHI

Basement (if any)100%

C 1 - Riddhi

Excavation100%

C 1 - RIDDHI

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

C 1 - Riddhi

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80%

C 1 - RIDDHI

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

C 1 - Riddhi

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing98%

C 1 - RIDDHI

Plinth100%
Podiums (if any) 100%

C 1 - Riddhi

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

C 1 - RIDDHI

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

C 1 - Riddhi

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

C 1 - RIDDHI

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

C 1 - Riddhi

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings 30%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 70%
Landscaping & Tree Planting 70%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting 90%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 20%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.