List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Saroj Serenity

by Olympeo Constructions Private Limited Company
Certificate SignedPM1271012500916
Saroj Serenity Project photos will appear here when available.

Project Information

RERA Certificate No.
PM1271012500916
Registration No.
ACK22082502928
Registration Date
2025-09-23
Developer
Olympeo Constructions Private Limited Company
Architect
Arunkumar
Project Bank
HDFC BANK
Proposed Possession
2030-10-30
Total Units
204
Units Sold
9 (4%)
Buildings
3
Project Area
7704.25 sq.m
Total FSI
16704.00
Approved FSI
11094.12
MahaRERA QR
Saroj Serenity
MahaRERA โ€” PM1271012500916
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors13
โœ…Sanctioned13
๐Ÿ Habitable13
๐Ÿ”ขTotal Units102
๐ŸกResidential102
๐Ÿ—๏ธProposed Floors13
โœ…Sanctioned13
๐Ÿ Habitable13
๐Ÿ”ขTotal Units102
๐ŸกResidential102

Construction Progress

Wing B

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth25%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Wing C

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โฌœEnergy managemcnt
โฌœFire protection and fire safety requirements
โœ…Internal Roads & Footpaths15%
โœ…Landscaping & Tree Planting
โœ…Open Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โœ…Solid Waste Management And Disposal
โœ…Storm Water Drains
โœ…Street Lighting
โœ…Treatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting