List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Shanti Garden

by Kamya Enterprises Partnership
Certificate SignedP51700007823
Shanti GardenProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700007823
Registration No.
REA51700020370
Registration Date
2021-09-09
Developer
Kamya Enterprises Partnership
Architect
Mrs Nailah Iqbal Mukadam
Project Bank
BANK OF BARODA
Proposed Possession
2021-12-30
Revised Possession
2021-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
5
Project Area
5903.28 sq.m
Total FSI
6358.79
Approved FSI
6358.79
MahaRERA QR
Shanti Garden
MahaRERA โ€” P51700007823
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors27
โœ…Sanctioned27
๐Ÿ—๏ธProposed Floors24
โœ…Sanctioned24
๐Ÿ—๏ธProposed Floors24
โœ…Sanctioned24
๐Ÿ—๏ธProposed Floors24
โœ…Sanctioned24
๐Ÿ—๏ธProposed Floors24
โœ…Sanctioned24

Apartment Configurations

SHANTI GARDEN A WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.14972
78%
1 BHK31.2710100
100%
1 BHK38.53101
0%
1 BHK39.11101
0%
1 BHK40.0211
50%
1 BHK40.12110
100%
1 BHK40.43110
100%
2 BHK45.88110
100%
2 BHK46.84110
100%
2 BHK47.21321
67%
2 BHK47.32321
67%
3 BHK56.96330
100%
3 BHK57.1321
67%

SHANTI GARDEN B WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.714131
93%
2 BHK52.2614122
86%

SHANTI GARDEN C WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.714140
100%
2 BHK52.2614122
86%

SHANTI GARDEN D WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.71486
57%
2 BHK52.2614113
79%

SHANTI GARDEN E WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.71468
43%
2 BHK52.2614140
100%

Construction Progress

SHANTI GARDEN A WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

SHANTI GARDEN B WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

SHANTI GARDEN C WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

SHANTI GARDEN D WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

SHANTI GARDEN E WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โฌœEnergy managemcnt
โœ…Fire protection and fire safety requirements
โฌœInternal Roads & Footpaths
โฌœLandscaping & Tree Planting
โœ…Open Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โฌœSolid Waste Management And Disposal
โฌœStorm Water Drains
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news โ†’
CallWhatsApp
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now