RERA: A51800043517

SILVER ESTATE

by NANDA KAPILDEV SHARMA Individual
Certificate Signed P51700014444
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700014444
Registration No.
REA51700027254
Registration Date
2017-12-04
Developer
NANDA KAPILDEV SHARMA Individual
Architect
Vilas Kasar And Associates
Project Bank
BANK OF BARODA
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
2022-06-30
Units Sold
0
Buildings
2
Project Area
2830.00 sq.m
Total FSI
2120.30
Approved FSI
2120.30
MahaRERA QR
SILVER ESTATE
MahaRERA — P51700014444
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
Sanctioned6
🅿️Closed Parking11
📅Completion2019-12-31
🏗️Proposed Floors6
Sanctioned6
🅿️Closed Parking4
📅Completion2021-06-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Rk 29.6299991607666 0 0 0
0%
Wing A And Wing C 1762.9300537109375 0 0 0
0%

Building No 1

Type Carpet (sq.ft) Total Booked Available Status
WING A AND WING C 1762.93 32 32 0
100%

Building No 2

Type Carpet (sq.ft) Total Booked Available Status
1RK 29.63 16 6 10
38%

Construction Progress

BUILDING NO 1

Basement (if any)100%

Building No 1

Excavation100%

BUILDING NO 1

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%

Building No 1

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%

BUILDING NO 1

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No 1

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing65%

BUILDING NO 1

Plinth100%
Podiums (if any) 0%

Building No 1

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 1

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Building No 1

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%

BUILDING NO 1

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Building No 1

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing50%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO 2

Basement (if any)100%

Building No 2

Excavation100%

BUILDING NO 2

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building No 2

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO 2

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building No 2

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUILDING NO 2

Plinth100%
Podiums (if any) 0%

Building No 2

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 2

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Building No 2

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING NO 2

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building No 2

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space 40%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting 20%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting 30%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.