SWAMI CHINTAMANI

by MEENA SADASHIV AGALAVE Individual
Certificate Signed P51700010673
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700010673
Registration No.
REA51700021257
Registration Date
2017-08-31
Developer
MEENA SADASHIV AGALAVE Individual
Architect
Santosh Madan And Associates
Project Bank
IDBI BANK
Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
188.11 sq.m
Total FSI
884.79
Approved FSI
884.79
MahaRERA QR
SWAMI CHINTAMANI
MahaRERA — P51700010673
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🚗Open Parking3
🅿️Closed Parking4
📅Completion2018-12-31
🏗️Proposed Floors1
Sanctioned1
📅Completion1900-01-01

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1 Bhk Type A 35.54999923706055 0 0 0
0%
1 Bhk Type B 33.25 0 0 0
0%
1 Rk 25.739999771118164 0 0 0
0%
2 Bhk 46.2599983215332 0 0 0
0%
Office 23.84000015258789 0 0 0
0%
Office Type A 35.54999923706055 0 0 0
0%
Office Type B 31.299999237060547 0 0 0
0%
Office Type C 36.2599983215332 0 0 0
0%
Office Type D 43.349998474121094 0 0 0
0%
Office Type E 23.889999389648438 0 0 0
0%
Office Type F 33.25 0 0 0
0%

Swami Chintamani B Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK TYPE A 35.55 4 0 4
0%
1 BHK TYPE B 33.25 3 2 1
67%
1 RK 25.74 1 0 1
0%
2 BHK 46.26 4 1 3
25%
OFFICE TYPE A 35.55 2 0 2
0%
OFFICE TYPE B 31.3 1 1 0
100%
OFFICE TYPE C 36.26 3 1 2
33%
OFFICE TYPE D 43.35 1 1 0
100%
OFFICE TYPE E 23.89 1 1 0
100%
OFFICE TYPE F 33.25 1 1 0
100%

Swami Chintamani C Wing

Type Carpet (sq.ft) Total Booked Available Status
OFFICE 23.84 1 0 1
0%

Construction Progress

SWAMI CHINTAMANI B WING

Basement (if any)100%

Swami Chintamani B Wing

Excavation100%

SWAMI CHINTAMANI B WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%

Swami Chintamani B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate75%

SWAMI CHINTAMANI B WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%

Swami Chintamani B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85%
Overall Percentage of Completion of the work done For the entire Building /Wing80%

SWAMI CHINTAMANI B WING

Plinth100%
Podiums (if any) 0%

Swami Chintamani B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises70%

SWAMI CHINTAMANI B WING

Sanitary Fittings within the flats / premises70%
Slabs of Super Structure100%

Swami Chintamani B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%

SWAMI CHINTAMANI B WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%

Swami Chintamani B Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

SWAMI CHINTAMANI C WING

Basement (if any)0%

Swami Chintamani C Wing

Excavation0%

SWAMI CHINTAMANI C WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Swami Chintamani C Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

SWAMI CHINTAMANI C WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Swami Chintamani C Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

SWAMI CHINTAMANI C WING

Plinth0%
Podiums (if any) 0%

Swami Chintamani C Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

SWAMI CHINTAMANI C WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Swami Chintamani C Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

SWAMI CHINTAMANI C WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Swami Chintamani C Wing

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 75%
Energy management
Fire Protection And Fire Safety Requirements 75%
Landscaping & Tree Planting 75%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 90%
Solid Waste Management And Disposal
Storm Water Drains 50%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply 70%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.