List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Swanand Treo Building No 3 -Swami Gannayak

by Swanand Heights Partnership
Certificate SignedP51700013459
Swanand Treo Building No 3 -Swami GannayakProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700013459
Registration No.
REA51700024510
Registration Date
2017-11-13
Developer
Swanand Heights Partnership
Architect
Samarthya Engineers
Project Bank
HDFC BANK
Proposed Possession
2017-12-31
Revised Possession
2017-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
980.44 sq.m
Total FSI
829.77
Approved FSI
829.77
MahaRERA QR
Swanand Treo Building No 3 -Swami Gannayak
MahaRERA โ€” P51700013459
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors7
โœ…Sanctioned7

Apartment Configurations

BUILDING NO 3 - SWAMI GANNAYAK

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.7312210
17%
1 BHK32.561266
50%

Construction Progress

BUILDING NO 3 - SWAMI GANNAYAK

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space100%
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station100%
โฌœEnergy managemcnt
โœ…Fire protection and fire safety requirements100%
โฌœInternal Roads & Footpaths
โœ…Landscaping & Tree Planting
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
โฌœSolid Waste Management And Disposal
โฌœStorm Water Drains
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply100%
โœ…Water conservation /Rain water harvesting100%

Latest Mumbai Property News

View all news โ†’
CallWhatsApp
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now