List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Tulip N

by Royale Urbanspace Partnership
Certificate SignedP51700011791
Tulip NProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700011791
Registration No.
REA51700018786
Registration Date
2017-08-31
Developer
Royale Urbanspace Partnership
Architect
Triarch Design Studio
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
462.63 sq.m
Total FSI
2106.99
Approved FSI
2106.99
MahaRERA QR
Tulip N
MahaRERA โ€” P51700011791
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors6
โœ…Sanctioned6
๐Ÿ—๏ธProposed Floors6
โœ…Sanctioned6

Apartment Configurations

TULIP N4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.0827261
96%

TULIP N5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.0827252
93%

Construction Progress

TULIP N4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises5%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
Stilt Floor0%

TULIP N5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises5%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
Stilt Floor0%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โœ…Energy managemcnt50%
โฌœFire protection and fire safety requirements
โœ…Internal Roads & Footpaths20%
โœ…Landscaping & Tree Planting
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)80%
โฌœSolid Waste Management And Disposal
โœ…Storm Water Drains30%
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting