List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Uma Residency, Phase I

by Adarsh Infra Developers Partnership
Certificate SignedP51700011302
Uma Residency, Phase IProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700011302
Registration No.
REA51700021983
Registration Date
2020-06-17
Developer
Adarsh Infra Developers Partnership
Architect
Parth Consultant and Town Planners
Project Bank
STATE BANK OF INDIA
Proposed Possession
2026-08-31
Revised Possession
1900-01-01
Extended Possession
2025-08-31
Total Units
120
Units Sold
31 (26%)
Buildings
5
Project Area
4470.00 sq.m
Total FSI
3929.64
Approved FSI
3929.64
MahaRERA QR
Uma Residency, Phase I
MahaRERA โ€” P51700011302
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ Habitable5
๐Ÿ”ขTotal Units40
๐ŸกResidential40
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ”ขTotal Units20
๐ŸกResidential20
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ”ขTotal Units20
๐ŸกResidential20
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ”ขTotal Units20
๐ŸกResidential20
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ”ขTotal Units20
๐ŸกResidential20

Apartment Configurations

Building E4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK FLAT29.45101
0%
1 BHK FLAT30.6431
75%
1 BHK FLAT31.15404
0%
1 BHK FLAT32.01697
56%
1 RK FLAT20.7303
0%
1 RK FLAT21.812111
8%

Building F3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK FLAT29.3404
0%
1 BHK FLAT30.5116016
0%

Building F4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.3404
0%
1BHK30.5116133
81%

Building G1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK FLAT29.310010
0%
1 RK FLAT20.6510010
0%

Building G2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK FLAT29.310010
0%
1 RK FLAT20.6510010
0%

Construction Progress

Building E4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Building F3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Building F4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Building G1

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Building G2

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station95%
โœ…Energy managemcnt75%
โฌœFire protection and fire safety requirements
โœ…Internal Roads & Footpaths95%
โœ…Landscaping & Tree Planting95%
โœ…Open Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)95%
โฌœSolid Waste Management And Disposal
โœ…Storm Water Drains95%
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting80%