📞 +91 98200 30685 ✉️
RERA: A51800043517

VAIBHAVI CITY

by PRADIP GANPAT PAWAR Individual
Certificate Signed P51700012138
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700012138
Registration No.
REA51700020300
Registration Date
2017-09-01
Developer
PRADIP GANPAT PAWAR Individual
Architect
Vitan Consultants
Project Bank
G P PARSIK BANK
Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
2022-12-30
Units Sold
0
Buildings
3
Project Area
493.44 sq.m
Total FSI
493.44
Approved FSI
493.44
MahaRERA QR
VAIBHAVI CITY
MahaRERA — P51700012138
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking1
📅Completion2018-12-31
🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking1
📅Completion2018-12-31
🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking1
📅Completion2018-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 34.27000045776367 0 0 0
0%
2Bhk 40.41999816894531 0 0 0
0%

Building No 1

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 34.27 20 17 3
85%
2 BHK 40.42 5 3 2
60%

Building No 2

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 34.27 18 16 2
89%
2 BHK 40.42 4 1 3
25%

Building No 3

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 34.27 20 18 2
90%
2 BHK 40.42 6 6 0
100%

Construction Progress

BUILDING NO 1

Basement (if any)100%

Building No 1

Excavation100%

BUILDING NO 1

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%

Building No 1

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO 1

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%

Building No 1

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70%
Overall Percentage of Completion of the work done For the entire Building /Wing70%

BUILDING NO 1

Plinth100%
Podiums (if any) 100%

Building No 1

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises30%

BUILDING NO 1

Sanitary Fittings within the flats / premises30%
Slabs of Super Structure100%

Building No 1

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.30%

BUILDING NO 1

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%

Building No 1

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing70%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

BUILDING NO 2

Basement (if any)100%

Building No 2

Excavation100%

BUILDING NO 2

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%

Building No 2

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO 2

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%

Building No 2

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70%
Overall Percentage of Completion of the work done For the entire Building /Wing70%

BUILDING NO 2

Plinth100%
Podiums (if any) 100%

Building No 2

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises30%

BUILDING NO 2

Sanitary Fittings within the flats / premises30%
Slabs of Super Structure100%

Building No 2

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.30%

BUILDING NO 2

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%

Building No 2

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing70%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

BUILDING NO 3

Basement (if any)100%

Building No 3

Excavation100%

BUILDING NO 3

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building No 3

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO 3

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%

Building No 3

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises30%
Overall Percentage of Completion of the work done For the entire Building /Wing55%

BUILDING NO 3

Plinth100%
Podiums (if any) 100%

Building No 3

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 3

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Building No 3

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.20%

BUILDING NO 3

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%

Building No 3

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.