vardhaman vatika

by rashilifestyle Partnership
Certificate Signed P51700012802
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700012802
Registration No.
REA51700022624
Registration Date
2020-06-18
Developer
rashilifestyle Partnership
Architect
Salvi& Associats
Proposed Possession
2020-12-30
Revised Possession
2020-12-30
Extended Possession
2022-06-30
Units Sold
0
Buildings
4
Project Area
7243.55 sq.m
Total FSI
5489.02
Approved FSI
5489.02
MahaRERA QR
vardhaman vatika
MahaRERA — P51700012802
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
Sanctioned5
🚗Open Parking8
📅Completion2018-03-30
🏗️Proposed Floors5
Sanctioned5
🚗Open Parking8
📅Completion1900-01-01
🏗️Proposed Floors5
Sanctioned5
🚗Open Parking8
📅Completion1900-01-01
🏗️Proposed Floors5
Sanctioned5
🚗Open Parking5
📅Completion2018-03-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 28.709999084472656 0 0 0
0%
1Bhk 31.68000030517578 0 0 0
0%
1Bhk 32.41999816894531 0 0 0
0%
1Bhk 32.70000076293945 0 0 0
0%
1Bhk 33.81999969482422 0 0 0
0%
1Bhk 34.75 0 0 0
0%
1Bhk 36.13999938964844 0 0 0
0%
1Bhk 38.54999923706055 0 0 0
0%
1Bhk 39.66999816894531 0 0 0
0%
1Bhk 40.779998779296875 0 0 0
0%
1Bhk 40.880001068115234 0 0 0
0%
1Bhk 41.15999984741211 0 0 0
0%
1Bhk 45.2400016784668 0 0 0
0%
2Bhk 47.189998626708984 0 0 0
0%
2Bhk 50.90999984741211 0 0 0
0%
2Bhk 53.33000183105469 0 0 0
0%
2Bhk 56.4900016784668 0 0 0
0%
2Bhk 57.599998474121094 0 0 0
0%
2Bhk 59.63999938964844 0 0 0
0%

Building No 09

Type Carpet (sq.ft) Total Booked Available Status
1bhk 34.75 1 1 0
100%
1bhk 40.78 4 2 2
50%
1bhk 40.88 4 3 1
75%
2bhk 47.19 1 1 0
100%
2bhk 50.91 1 1 0
100%
2bhk 56.49 3 2 1
67%
2bhk 59.64 2 0 2
0%

Building No 10

Type Carpet (sq.ft) Total Booked Available Status
1bhk 32.42 1 1 0
100%
1bhk 32.7 1 1 0
100%
1bhk 33.82 1 1 0
100%
1bhk 38.55 4 1 3
25%
1bhk 39.67 5 0 5
0%
1bhk 41.16 4 1 3
25%
2bhk 57.6 3 0 3
0%

Building No 11

Type Carpet (sq.ft) Total Booked Available Status
1bhk 32.42 1 0 1
0%
1bhk 32.7 1 0 1
0%
1bhk 33.82 1 0 1
0%
1bhk 38.55 6 0 6
0%
1bhk 39.67 4 0 4
0%
1bhk 41.16 4 0 4
0%
2bhk 57.6 2 0 2
0%

Building No 8

Type Carpet (sq.ft) Total Booked Available Status
1bhk 28.71 1 1 0
100%
1bhk 31.68 3 3 0
100%
1bhk 36.14 1 0 1
0%
1bhk 45.24 4 3 1
75%
2bhk 53.33 3 1 2
33%

Construction Progress

building no 09

Basement (if any)100%

Building No 09

Excavation100%

building no 09

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No 09

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

building no 09

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No 09

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%

building no 09

Plinth100%
Podiums (if any) 0%

Building No 09

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

building no 09

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No 09

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

building no 09

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No 09

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

building no 10

Basement (if any)100%

Building No 10

Excavation100%

building no 10

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No 10

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

building no 10

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No 10

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%

building no 10

Plinth100%
Podiums (if any) 0%

Building No 10

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

building no 10

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No 10

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

building no 10

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No 10

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

building no 11

Basement (if any)100%

Building No 11

Excavation100%

building no 11

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No 11

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

building no 11

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No 11

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%

building no 11

Plinth100%
Podiums (if any) 0%

Building No 11

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

building no 11

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No 11

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

building no 11

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No 11

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

building no 8

Basement (if any)100%

Building No 8

Excavation100%

building no 8

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No 8

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

building no 8

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No 8

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%

building no 8

Plinth100%
Podiums (if any) 0%

Building No 8

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

building no 8

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No 8

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

building no 8

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No 8

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 10%
ampi theater 10%
club house 10%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 10%
Energy management
Fire Protection And Fire Safety Requirements
gymnasuim 10%
Landscaping & Tree Planting 10%
library room 10%
Open Parking 10%
playing area 10%
Sewerage (Chamber, Lines, Septic Tank , STP) 10%
skating ring 10%
Solid Waste Management And Disposal
Storm Water Drains 10%
Street Lighting 10%
Treatment And Disposal Of Sewage And Sullage Water 10%
Water Conservation, Rain water Harvesting
Water Supply 10%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.