VEENA DYNASTY PH II

by NIKUNJ DEVELOPERS Partnership
Certificate SignedP99000007769

Project Information

RERA Certificate No.
P99000007769
Registration No.
REA99000011395
Registration Date
2017-08-18
Developer
NIKUNJ DEVELOPERS Partnership
Architect
Krutika Enterprises
Project Bank
RBL Bank Limited
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
11
Project Area
8130.00 sq.m
Total FSI
16041.61
Approved FSI
16041.61
MahaRERA QR
VEENA DYNASTY PH II
MahaRERA — P99000007769
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🚗Open Parking6
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🚗Open Parking13
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🚗Open Parking14
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🚗Open Parking16
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🚗Open Parking15
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🚗Open Parking12
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🚗Open Parking9
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🚗Open Parking8
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🚗Open Parking15
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🚗Open Parking15
🅿️Closed Parking1
📅Completion2019-12-31
🏗️Proposed Floors9
Sanctioned9
🚗Open Parking14
🅿️Closed Parking1
📅Completion2019-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 Bhk31.450000762939453000
0%
1 Bhk33.7400016784668000
0%
1 Bhk33.88999938964844000
0%
1 Bhk33.9900016784668000
0%
1 Bhk34.13999938964844000
0%
1 Bhk34.18000030517578000
0%
1 Bhk34.20000076293945000
0%
1 Bhk34.209999084472656000
0%
1 Bhk34.40999984741211000
0%
1 Bhk34.66999816894531000
0%
1 Bhk40.08000183105469000
0%
1Bhk33.88999938964844000
0%
1Bhk34.189998626708984000
0%
1Bhk34.40999984741211000
0%
1Bhk34.68000030517578000
0%
2 Bhk47.41999816894531000
0%
2 Bhk49.0000
0%
2 Bhk50.16999816894531000
0%
2 Bhk50.470001220703125000
0%
2 Bhk50.529998779296875000
0%
2 Bhk51.599998474121094000
0%
2Bhk46.869998931884766000
0%
2Bhk47.41999816894531000
0%
Shop9.890000343322754000
0%
Shop9.899999618530273000
0%
Shop10.029999732971191000
0%
Shop11.520000457763672000
0%
Shop12.520000457763672000
0%
Shop12.720000267028809000
0%
Shop13.350000381469727000
0%
Shop13.359999656677246000
0%
Shop13.680000305175781000
0%
Shop13.920000076293945000
0%
Shop15.899999618530273000
0%
Shop33.34000015258789000
0%

Wing A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.8914140
100%
1 BHK34.214140
100%
SHOP9.89110
100%
SHOP9.9110
100%
SHOP13.35110
100%
SHOP13.36330
100%

Wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.45761
86%
1 BHK34.18770
100%
1 BHK34.19770
100%
1 BHK34.21660
100%
SHOP9.9220
100%
SHOP10.03110
100%
SHOP13.36330
100%

Wing C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.14770
100%
1 BHK34.6714140
100%
1 BHK34.68110
100%
1 BHK40.08110
100%
2 BHK47.42862
75%
2 BHK49.0770
100%
2 BHK50.47651
83%
2 BHK50.53110
100%
SHOP11.52110
100%
SHOP12.52110
100%
SHOP12.72110
100%
SHOP13.68110
100%
SHOP13.92220
100%
SHOP15.9110
100%
SHOP33.34110
100%

Wing D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.89330
100%
1 BHK34.4127270
100%

Wing E

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.4129290
100%

Wing F

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.4231310
100%

Wing G

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.4231310
100%

Wing H

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.4129290
100%

Wing I

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.8930300
100%

Wing J

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.7415150
100%
1 BHK33.99880
100%
2 BHK46.8716151
94%
2 BHK51.6880
100%

Wing K

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.4223230
100%
2 BHK50.17880
100%

Construction Progress

WING A

Basement (if any)100%

Wing A

Excavation100%

WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING A

Plinth100%
Podiums (if any) 0%

Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING A

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing A

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING B

Basement (if any)100%

Wing B

Excavation100%

WING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING B

Plinth100%
Podiums (if any) 0%

Wing B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING B

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing B

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING C

Basement (if any)100%

Wing C

Excavation100%

WING C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING C

Plinth100%
Podiums (if any) 0%

Wing C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING C

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing C

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING D

Basement (if any)100%

Wing D

Excavation100%

WING D

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing D

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING D

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing D

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING D

Plinth100%
Podiums (if any) 0%

Wing D

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING D

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing D

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING D

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing D

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING E

Basement (if any)100%

Wing E

Excavation100%

WING E

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing E

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING E

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing E

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING E

Plinth100%
Podiums (if any) 0%

Wing E

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING E

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing E

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING E

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing E

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING F

Basement (if any)100%

Wing F

Excavation100%

WING F

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing F

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING F

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing F

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING F

Plinth100%
Podiums (if any) 0%

Wing F

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING F

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing F

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING F

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing F

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING G

Basement (if any)100%

Wing G

Excavation100%

WING G

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing G

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING G

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing G

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING G

Plinth100%
Podiums (if any) 0%

Wing G

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING G

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing G

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING G

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing G

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING H

Basement (if any)100%

Wing H

Excavation100%

WING H

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing H

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING H

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing H

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING H

Plinth100%
Podiums (if any) 0%

Wing H

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING H

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing H

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING H

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing H

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING I

Basement (if any)100%

Wing I

Excavation100%

WING I

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing I

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING I

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing I

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING I

Plinth100%
Podiums (if any) 0%

Wing I

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING I

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing I

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING I

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing I

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING J

Basement (if any)100%

Wing J

Excavation100%

WING J

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing J

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING J

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing J

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING J

Plinth100%
Podiums (if any) 0%

Wing J

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING J

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing J

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING J

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing J

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING K

Basement (if any)100%

Wing K

Excavation100%

WING K

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing K

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING K

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing K

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING K

Plinth100%
Podiums (if any) 0%

Wing K

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING K

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing K

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING K

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing K

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space50%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management
Fire Protection And Fire Safety Requirements100%
Landscaping & Tree Planting100%
Open Parking50%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal40%
Storm Water Drains100%
Street Lighting100%
Treatment And Disposal Of Sewage And Sullage Water100%
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.