ADITYA RESIDENCY

by ADITI DEVELOPERS Partnership
Certificate SignedPR1240002502671
ADITYA RESIDENCYProject photos will appear here when available.

Project Information

RERA Certificate No.
PR1240002502671
Registration No.
PR1240002502671
Registration Date
2026-03-09
Developer
ADITI DEVELOPERS Partnership
Proposed Possession
2030-04-30
Revised Possession
2029-12-31
Total Units
115
Units Sold
0 (0%)
Buildings
1
Project Area
6749.99 sq.m
MahaRERA QR
ADITYA RESIDENCY
MahaRERA โ€” PR1240002502671
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable7
๐Ÿ”ขTotal Units59
๐ŸกResidential59
๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable7
๐Ÿ”ขTotal Units56
๐ŸกResidential56

Construction Progress

Aditya Residency - Building No 2

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor60%

Aditya Residency - Building No 3

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โฌœElectrical meter room, sub-station, receiving station
โฌœEnergy managemcnt
โฌœFire protection and fire safety requirements
โฌœInternal Roads & Footpaths
โœ…Landscaping & Tree Planting
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โฌœSolid Waste Management And Disposal
โฌœStorm Water Drains
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting