AKSHAR RIVERGATE PLOT B

by EMPERIA REALTY Partnership
Certificate Signed P52000032008
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P52000032008
Registration No.
REA52000096591
Registration Date
2021-12-03
Developer
EMPERIA REALTY Partnership
Architect
Destination Architecture Interior Designs
Project Bank
IDBI BANK
Proposed Possession
2025-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
4
Project Area
5770.00 sq.m
Total FSI
8533.00
MahaRERA QR
AKSHAR RIVERGATE PLOT B
MahaRERA — P52000032008
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
Sanctioned8
📅Completion2025-12-31
🏗️Proposed Floors8
Sanctioned8
📅Completion2025-12-31
🏗️Proposed Floors8
Sanctioned8
📅Completion2025-12-31
🏗️Proposed Floors6
Sanctioned6
📅Completion2025-12-31

Apartment Configurations

B1

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.446 7 0 7
0%
1 BHK 31.84 7 0 7
0%
1 BHK 32.178 14 0 14
0%
2 BHK 42.908 14 0 14
0%
2 BHK 45.662 7 0 7
0%

B2

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.367 14 0 14
0%
1 BHK 29.493 28 0 28
0%
2 BHK 42.908 14 0 14
0%

B3

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.446 7 0 7
0%
1 BHK 31.178 14 0 14
0%
1 BHK 31.84 7 0 7
0%
2 BHK 42.908 14 0 14
0%
2 BHK 45.662 7 0 7
0%

B4

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.367 20 0 20
0%
1 BHK 31.84 10 0 10
0%
1RK 23.203 20 0 20
0%

Construction Progress

B1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
Stilt Floor 100%

B2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

B3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

B4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.