A
✓ MahaRERA P52000053112RERA: no litigation reported24
Units
2029
Possession
1
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Dec 2029
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 BHK424–450 ft²On request
2 BHK611 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P52000053112
Registered
2023-10-16
Litigation
No reported in source
Escrow Bank
IDBI BANK
Architect
Monika Patil
Total FSI
1262
04
Buildings · 1 Wing(s)
Alibag Nirvana7 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Chendhare
18.656707630227586,72.88038456505775
18.656707630227586,72.88038456505775
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
Chirag AjmeraPartner
Hardik AjmeraPartner
Varun Mayur AjmeraPartner
09
Construction Progress
74% avgBasement (if any)100%
Excavation100%
Plinth100%
Slabs of Super Structure100%
Stilt Floor 100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Sanitary Fittings within the flats / premises50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Podiums (if any) 0%
10
Amenities
Fire Protection And Fire Safety RequirementsSewerage (Chamber, Lines, Septic Tank , STP)Water Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory08
Property Rates in Chendhare
Residential · Sale
₹4,000–65,000/sqft
Commercial · Sale
₹3,500–10,000/sqft
2 BHK · Rent
₹15,000–40,000/mo
Full rates
14
More by ACORP
15
MahaRERA projects nearby in Chendhare
?
Frequently Asked Questions
When is possession of Alibag Nirvana?
As per MahaRERA, proposed possession is Dec 2029.
Is Alibag Nirvana RERA-registered?
Yes — MahaRERA registration P52000053112, registered 2023-10-16. The current MahaRERA source record reports no litigations.
Who is the developer?
ACORP — 1 projects tracked on Mumbai Property Exchange. View their track record ▸