📞 +91 98200 30685 ✉️
RERA: A51800043517

ARIHANT ANMOL PHASE II

by ARIHANT VATIKA REALTY PRIVATE LIMITED Company
Certificate Signed P51700003112
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700003112
Registration No.
REA51700008313
Registration Date
2020-06-11
Developer
ARIHANT VATIKA REALTY PRIVATE LIMITED Company
Architect
Kiran K Awhale
Project Bank
ICICI BANK LIMITED
Proposed Possession
2020-09-30
Revised Possession
2020-09-30
Extended Possession
2022-03-30
Units Sold
0
Buildings
3
Project Area
4223.79 sq.m
Total FSI
10389.84
Approved FSI
10389.84
MahaRERA QR
ARIHANT ANMOL PHASE II
MahaRERA — P51700003112
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors13
Sanctioned13
🅿️Closed Parking29
📅Completion2020-03-30
🏗️Proposed Floors13
Sanctioned13
🅿️Closed Parking27
📅Completion2020-03-30
🏗️Proposed Floors12
Sanctioned12
🅿️Closed Parking29
📅Completion2020-03-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1 Bhk 28.729999542236328 0 0 0
0%
1 Bhk 29.34000015258789 0 0 0
0%
2 Bhk 40.70000076293945 0 0 0
0%
Shop No. 1 And 6 9.520000457763672 0 0 0
0%
Shop No. 10 And 11 18.700000762939453 0 0 0
0%
Shop No. 12 16.110000610351562 0 0 0
0%
Shop No. 13 14.949999809265137 0 0 0
0%
Shop No. 14 18.829999923706055 0 0 0
0%
Shop No. 16 9.520000457763672 0 0 0
0%
Shop No. 2 And 5 18.540000915527344 0 0 0
0%
Shop No. 3 And 4 18.030000686645508 0 0 0
0%
Shop No. 7 12.59000015258789 0 0 0
0%
Shop No. 8 9.520000457763672 0 0 0
0%
Shop No. 9 And 15 17.989999771118164 0 0 0
0%

B2

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.34 23 23 0
100%
2 BHK 40.7 48 48 0
100%
SHOP NO. 10 AND 11 18.7 2 2 0
100%
SHOP NO. 12 16.11 1 1 0
100%
SHOP NO. 13 14.95 1 1 0
100%
SHOP NO. 14 18.83 1 1 0
100%
SHOP NO. 16 9.52 1 1 0
100%
SHOP NO. 8 9.52 1 1 0
100%
SHOP NO. 9 AND 15 17.99 2 2 0
100%

B3

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 28.73 36 36 0
100%
2 BHK 40.7 36 36 0
100%
SHOP NO. 1 AND 6 9.52 2 1 1
50%
SHOP NO. 2 AND 5 18.54 2 1 1
50%
SHOP NO. 3 AND 4 18.03 2 1 1
50%
SHOP NO. 7 12.59 1 1 0
100%

Construction Progress

B1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

B2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

B3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 80%
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 80%
Energy management
Fire Protection And Fire Safety Requirements 95%
Landscaping & Tree Planting 80%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 50%
Water Supply 95%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.