✓ MahaRERA P51700003112RERA: no litigation reported159
Units
2020
Possession
3
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: Ongoing · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Sep 2020
Revised
Sep 2020
Status
Ongoing
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 BHK309–316 ft²On request
2 BHK438 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51700003112
Registered
2020-06-11
Litigation
No reported in source
Escrow Bank
ICICI BANK LIMITED
Architect
Kiran K Awhale
Total FSI
10389
04
Buildings · 3 Wing(s)
B113 floors · — units
B213 floors · — units
B312 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Badlapur
19.144811000000001,73.243465999999998
19.144811000000001,73.243465999999998
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
ARIHANT VATIKA REALTY PRIVATE LIMITEDNA
ASHOKKUMAR BHANWARLAL CHHAJERDIRECTOR
YOGITA BHANDARKARArchitect
09
Construction Progress
91% avgBasement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
Podiums (if any) 0%
10
Amenities
Aggregate area of recreational Open SpaceCommunity BuildingsElectrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsInternal Roads & FootpathsLandscaping & Tree PlantingLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory08
Property Rates in Badlapur
Residential · Sale
₹6,000–10,000/sqft
Commercial · Sale
₹6,500–7,500/sqft
2 BHK · Rent
₹10,000–20,000/mo
Full rates
14
More by Arihant Vatika Realty
15
MahaRERA projects nearby in Badlapur
Pradhan Mantri Awas Yojana - Urban2352 unitsShreeji Milestone575 unitsSky Gardens At Godrej Vihaa495 unitsShreeji Square Phase I425 unitsTrident Woods423 unitsShreeji Greens383 unitsTulsi Aanand320 unitsSWANAND VEDIKA305 unitsTulsi Aananta277 unitsTrident Vrindavan244 unitsPark One, Phase I220 unitsOrient Legacy219 units
?
Frequently Asked Questions
When is possession of Arihant Anmol Phase II?
As per MahaRERA, proposed possession is Sep 2020, revised to Sep 2020.
Is Arihant Anmol Phase II RERA-registered?
Yes — MahaRERA registration P51700003112, registered 2020-06-11. The current MahaRERA source record reports no litigations.
Who is the developer?
Arihant Vatika Realty — 47 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.