01
Possession Timeline
Proposed
Jun 2024
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 BHK388–396 ft²On request
2 BHK576 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P52000033832
Registered
2022-03-08
Litigation
No reported in source
Escrow Bank
ICICI BANK LIMITED
Architect
—
Total FSI
6922
04
Buildings · 3 Wing(s)
A -Wing9 floors · — units
B -Wing9 floors · — units
C - Wing9 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Alibaug
▸ Explore map & Street View — for verified buyers
09
Construction Progress
91% avgBasement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
Podiums (if any) 0%
10
Amenities
Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsStreet LightingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory08
Property Rates in Alibaug
Residential · Sale
₹4,000–65,000/sqft
Commercial · Sale
₹3,500–10,000/sqft
2 BHK · Rent
₹15,000–40,000/mo
Full rates
14
More by Balaji Vishwakarma Associates
15
MahaRERA projects nearby in Alibaug
?
Frequently Asked Questions
When is possession of Balaji Palms Phase - II?
As per MahaRERA, proposed possession is Jun 2024.
Is Balaji Palms Phase - II RERA-registered?
Yes — MahaRERA registration P52000033832, registered 2022-03-08. The current MahaRERA source record reports no litigations.
Who is the developer?
Balaji Vishwakarma Associates — 20 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.