B
✓ MahaRERA P52000045608RERA: no litigation reported147
Units
2025
Possession
1
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Nov 2025
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Shop92–173 ft²On request
1 BHK349–360 ft²On request
1 BHK Floor349–434 ft²On request
2 BHK413–566 ft²On request
2 BHK Floor417–566 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P52000045608
Registered
2022-05-26
Litigation
No reported in source
Escrow Bank
INDIAN OVERSEAS BANK
Architect
Satish Manohar
Total FSI
12705
04
Buildings · 1 Wing(s)
Mariette Maureen11 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Mohopada
21.897400300000000,83.394963199999990
21.897400300000000,83.394963199999990
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
Debjani RameshPartner
Mahesh Kumar NagarajanPartner
09
Construction Progress
41% avgBasement (if any)100%
Excavation100%
Plinth100%
Stilt Floor 100%
Slabs of Super Structure55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
10
Amenities
Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationEnergy managementFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsWater Conservation, Rain water Harvesting
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory14
More by Balaji Homes
?
Frequently Asked Questions
When is possession of Balaji Tulips?
As per MahaRERA, proposed possession is Nov 2025.
Is Balaji Tulips RERA-registered?
Yes — MahaRERA registration P52000045608, registered 2022-05-26. The current MahaRERA source record reports no litigations.
Who is the developer?
Balaji Homes — 20 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.