BHAGWATI ELEGANZA

by BHAGWATI DEVELOPERS Partnership
Certificate Signed P51700003864
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700003864
Registration No.
REA51700013814
Registration Date
2017-08-06
Developer
BHAGWATI DEVELOPERS Partnership
Architect
Soyuz Talib Architects Pvt Ltd
Project Bank
BANK OF INDIA
Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
5
Project Area
9696.16 sq.m
Total FSI
14544.24
Approved FSI
14517.82
MahaRERA QR
BHAGWATI ELEGANZA
MahaRERA — P51700003864
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors3
Sanctioned3
🅿️Closed Parking31
📅Completion2018-12-31
🏗️Proposed Floors41
Sanctioned41
🅿️Closed Parking105
📅Completion2018-12-31
🏗️Proposed Floors41
Sanctioned41
🅿️Closed Parking105
📅Completion2018-03-31
🏗️Proposed Floors41
Sanctioned41
🅿️Closed Parking105
📅Completion2018-03-31
🏗️Proposed Floors31
Sanctioned31
🅿️Closed Parking54
📅Completion2018-03-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
Shop Type 1 55.41999816894531 0 0 0
0%
Shop Type 2 60.72999954223633 0 0 0
0%
Shop Type 3 66.80999755859375 0 0 0
0%
Type 1 34.9900016784668 0 0 0
0%
Type 1 43.0099983215332 0 0 0
0%
Type 1 44.4900016784668 0 0 0
0%
Type 2 57.16999816894531 0 0 0
0%

Shopping

Type Carpet (sq.ft) Total Booked Available Status
SHOP TYPE 1 55.42 16 16 0
100%
SHOP TYPE 2 60.73 5 5 0
100%
SHOP TYPE 3 66.81 3 3 0
100%

Wing A

Type Carpet (sq.ft) Total Booked Available Status
TYPE 1 44.49 35 35 0
100%
TYPE 2 57.17 35 35 0
100%

Wing B

Type Carpet (sq.ft) Total Booked Available Status
TYPE 1 43.01 70 56 14
80%

Wing C

Type Carpet (sq.ft) Total Booked Available Status
TYPE 1 44.49 35 35 0
100%
TYPE 2 57.17 35 35 0
100%

Wing D

Type Carpet (sq.ft) Total Booked Available Status
TYPE 1 34.99 50 50 0
100%

Construction Progress

SHOPPING

Basement (if any)100%

Shopping

Excavation100%

SHOPPING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Shopping

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

SHOPPING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Shopping

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

SHOPPING

Plinth100%
Podiums (if any) 100%

Shopping

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

SHOPPING

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Shopping

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SHOPPING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Shopping

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

WING A

Basement (if any)100%

Wing A

Excavation100%

WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

WING A

Plinth100%
Podiums (if any) 100%

Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING A

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing A

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

WING B

Basement (if any)100%

Wing B

Excavation100%

WING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

WING B

Plinth100%
Podiums (if any) 100%

Wing B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING B

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing B

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

WING C

Basement (if any)100%

Wing C

Excavation100%

WING C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

WING C

Plinth100%
Podiums (if any) 100%

Wing C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING C

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing C

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

WING D

Basement (if any)100%

Wing D

Excavation100%

WING D

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing D

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING D

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing D

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

WING D

Plinth100%
Podiums (if any) 100%

Wing D

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING D

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing D

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING D

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing D

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.