📞 +91 98200 30685 ✉️
RERA: A51800043517

D4 IRIS

by Neelkanth Mansions and Infrastructure Pvt. Ltd. Company
Certificate Signed P51700000552
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700000552
Registration No.
REA51700004117
Registration Date
2020-06-11
Developer
Neelkanth Mansions and Infrastructure Pvt. Ltd. Company
Architect
Saakaar Architects
Project Bank
HDFC BANK
Proposed Possession
2020-09-30
Revised Possession
2020-09-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
1751.85 sq.m
Total FSI
8445.88
Approved FSI
8445.88
MahaRERA QR
D4 IRIS
MahaRERA — P51700000552
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors33
Sanctioned33
🚗Open Parking22
🅿️Closed Parking158
📅Completion2020-03-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2Bhk 64.58000183105469 0 0 0
0%
3 Bhk 91.95999908447266 0 0 0
0%

Iris

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 64.58 50 43 7
86%
3 BHK 91.96 54 33 21
61%

Construction Progress

IRIS

Basement (if any)100%

Iris

Excavation100%

IRIS

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Iris

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

IRIS

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Iris

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

IRIS

Plinth100%
Podiums (if any) 100%

Iris

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

IRIS

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Iris

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

IRIS

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Iris

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.