✓ MahaRERA P51700048333RERA: no litigation reportedDgt - Sector 3A - Cluster 2
Registered MahaRERA name: Dgt - Sector 3A - Cluster 2 - Phase 3
📍 Kalher Junction, Thane · 421302
710
Units
2028
Possession
1
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Jun 2028
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
2 BHK452–535 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51700048333
Registered
2023-09-08
Litigation
No reported in source
Escrow Bank
HDFC BANK
Architect
Spaceage Consultants
Total FSI
53688
04
Buildings · 1 Wing(s)
Dosti Grace - Wing A - Tower T4-5 And Wing B - To— floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Kalher Junction
19.2451968,73.0179393
19.2451968,73.0179393
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
ADRIKA DEVELOPERS PRIVATE LIMITEDNA
ARCHITECT JAY R VORAArchitect
DEEPAK KISHAN GORADIADirector
RAJESH PREMJI SHAHDirector
RAJUL VRAJLAL VORADirector
09
Construction Progress
52% avgBasement (if any)100%
Excavation100%
Plinth100%
Slabs of Super Structure100%
Stilt Floor 100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks39%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises28%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
10
Amenities
Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationEnergy managemcntEnergy managementFire Protection And Fire Safety RequirementsInternal Roads & FootpathsLandscaping & Tree PlantingLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory15
MahaRERA projects nearby in Kalher Junction
Dgt - Sector 3A - Cluster 2 - Phase 11836 unitsDosti Greater Thane - Sector 3A - Cluster 1B - Phase 11025 unitsDgt - Sector 3A - Cluster 2 - Phase 2830 unitsDosti Greater Thane - Sector 3A - Cluster 1B - Phase 3682 unitsDgt - Sector 3A - Cluster 2 - Phase 4355 unitsDosti Greater Thane - Sector 3A - Cluster 1B - Phase 2339 units
?
Frequently Asked Questions
When is possession of Dgt - Sector 3A - Cluster 2?
As per MahaRERA, proposed possession is Jun 2028.
Is Dgt - Sector 3A - Cluster 2 RERA-registered?
Yes — MahaRERA registration P51700048333, registered 2023-09-08. The current MahaRERA source record reports no litigations.
Who is the developer?
Adrika Developers View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.