Project Information

RERA Certificate No.
P51700003667
Registration No.
REA51700012075
Registration Date
2017-08-06
Developer
DEV KONARK CORPORATION Others
Architect
Ravindra Ghormode
Proposed Possession
2018-09-30
Revised Possession
2018-09-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
4
Project Area
1742.71 sq.m
Total FSI
2956.83
Approved FSI
2956.83
MahaRERA QR
ENTILLA BY DEV
MahaRERA — P51700003667
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
Sanctioned6
📅Completion2018-09-30
🏗️Proposed Floors6
Sanctioned6
📅Completion2018-09-30
🏗️Proposed Floors6
Sanctioned6
📅Completion2018-09-30
🏗️Proposed Floors6
Sanctioned6
📅Completion2018-09-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1 Bhk 29.600000381469727 0 0 0
0%
1 Bhk 29.700000762939453 0 0 0
0%
1 Bhk Flat 20.65999984741211 0 0 0
0%
1 Bhk Flat 24.3799991607666 0 0 0
0%
1 Bhk Flat 26.6200008392334 0 0 0
0%
1 Bhk Flat 26.850000381469727 0 0 0
0%
1 Bhk Flat 27.209999084472656 0 0 0
0%
1 Bhk Flat 28.309999465942383 0 0 0
0%
1 Bhk Flat 30.15999984741211 0 0 0
0%
1 Bhk Flat 30.229999542236328 0 0 0
0%
1 Bhk Flat 32.970001220703125 0 0 0
0%
2 Bhk 39.029998779296875 0 0 0
0%
2 Bhk Flat 36.209999084472656 0 0 0
0%
2 Bhk Flat 36.91999816894531 0 0 0
0%
Shop 5.639999866485596 0 0 0
0%
Shop 6.340000152587891 0 0 0
0%
Shop 6.659999847412109 0 0 0
0%
Shop 7.269999980926514 0 0 0
0%
Shop 7.389999866485596 0 0 0
0%
Shop 7.460000038146973 0 0 0
0%
Shop 7.510000228881836 0 0 0
0%
Shop 7.630000114440918 0 0 0
0%
Shop 8.25 0 0 0
0%
Shop 8.380000114440918 0 0 0
0%
Shop 11.130000114440918 0 0 0
0%
Shop 12.75 0 0 0
0%
Shop 16.969999313354492 0 0 0
0%
Shop 17.829999923706055 0 0 0
0%
Shop 20.049999237060547 0 0 0
0%
Shop 22.670000076293945 0 0 0
0%
Shop 84.12000274658203 0 0 0
0%
Shop 173.22999572753906 0 0 0
0%

Wing A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK FLAT 20.66 4 2 2
50%
1 BHK FLAT 24.38 4 3 1
75%
1 BHK FLAT 26.85 8 6 2
75%
SHOP 5.64 2 2 0
100%
SHOP 6.34 1 1 0
100%
SHOP 7.27 1 1 0
100%
SHOP 11.13 1 1 0
100%
SHOP 16.97 1 0 1
0%

Wing B

Type Carpet (sq.ft) Total Booked Available Status
1 BHK FLAT 27.21 12 10 2
83%
2 BHK FLAT 36.92 4 4 0
100%
SHOP 5.64 2 2 0
100%
SHOP 7.46 2 2 0
100%
SHOP 8.38 1 1 0
100%
SHOP 17.83 1 1 0
100%

Wing C

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.6 8 6 2
75%
1 BHK 29.7 4 0 4
0%
2 BHK 39.03 4 4 0
100%
SHOP 6.66 2 2 0
100%
SHOP 7.51 1 1 0
100%
SHOP 7.63 1 1 0
100%
SHOP 12.75 1 1 0
100%
SHOP 22.67 1 0 1
0%

Wing D

Type Carpet (sq.ft) Total Booked Available Status
1 BHK FLAT 26.62 3 0 3
0%
1 BHK FLAT 28.31 3 2 1
67%
1 BHK FLAT 30.16 4 0 4
0%
1 BHK FLAT 30.23 4 3 1
75%
1 BHK FLAT 32.97 3 0 3
0%
2 BHK FLAT 36.21 3 2 1
67%
SHOP 7.39 1 1 0
100%
SHOP 8.25 1 0 1
0%
SHOP 20.05 1 0 1
0%
SHOP 84.12 1 1 0
100%
SHOP 173.23 1 1 0
100%

Construction Progress

WING A

Basement (if any)100%

Wing A

Excavation100%

WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING A

Plinth100%
Podiums (if any) 0%

Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING A

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing A

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING B

Basement (if any)100%

Wing B

Excavation100%

WING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING B

Plinth100%
Podiums (if any) 0%

Wing B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING B

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing B

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING C

Basement (if any)100%

Wing C

Excavation100%

WING C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%

Wing C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%

Wing C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90%
Overall Percentage of Completion of the work done For the entire Building /Wing71%

WING C

Plinth100%
Podiums (if any) 0%

Wing C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises75%

WING C

Sanitary Fittings within the flats / premises75%
Slabs of Super Structure100%

Wing C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.75%

WING C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%

Wing C

Stilt Floor80%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING D

Basement (if any)100%

Wing D

Excavation100%

WING D

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%

Wing D

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING D

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%

Wing D

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%
Overall Percentage of Completion of the work done For the entire Building /Wing62%

WING D

Plinth100%
Podiums (if any) 0%

Wing D

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

WING D

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%

Wing D

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.75%

WING D

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%

Wing D

Stilt Floor70%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing75%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 50%
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting 25%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 50%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 50%
Water Supply 50%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.