HARBANS PARK PHASE 3

by HARBANS CREATION (AOP) AOP/BOI
Certificate SignedPR1190002501795
HARBANS PARK PHASE 3Project photos will appear here when available.

Project Information

RERA Certificate No.
PR1190002501795
Registration No.
PR1190002501795
Registration Date
2025-12-15
Developer
HARBANS CREATION (AOP) AOP/BOI
Proposed Possession
2028-04-30
Revised Possession
2027-12-31
Total Units
27
Units Sold
9 (33%)
Buildings
27
Project Area
4536.60 sq.m
MahaRERA QR
HARBANS PARK PHASE 3
MahaRERA โ€” PR1190002501795
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors3
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1

Construction Progress

HARBANS PARK PHASE 3 A-1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises30%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

HARBANS PARK PHASE 3 A-2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 A-3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 A-4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 A-5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 A-6

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 A-7

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 A-8

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 A-9

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 B-1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 B-2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 B-3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 B-4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 B-5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 B-6

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 B-7

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 B-8

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 B-9

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 C-1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 C-2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 C-3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 C-4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 C-5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 C-6

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 C-7

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 C-8

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

HARBANS PARK PHASE 3 C-9

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor0%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โฌœEnergy managemcnt
โฌœFire protection and fire safety requirements
โฌœInternal Roads & Footpaths
โฌœLandscaping & Tree Planting
โœ…Open Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
โฌœSolid Waste Management And Disposal
โฌœStorm Water Drains
โฌœStreet Lighting
โœ…Treatment And Disposal Of Sewage And Sullage Water100%
โœ…Water Supply100%
โœ…Water conservation /Rain water harvesting100%