List PropertyWhatsApp
New ProjectsBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your PropertyπŸ’¬ WhatsApp Us
πŸ† Mumbai's oldest property portalSince 1995βœ“ MahaRERA A51800043517βœ“ RERA-verified project data🟒 We reply in minutes on WhatsApp
H
βœ“ MahaRERA P51700004551βœ“ Clear

Heramb Park Phase II by Sai Samruddhi Construction Co

Sai Samruddhi Construction Co
πŸ“ Ambarnath, Thane Β· 421503
125
Units
2019
Possession
2
Buildings
Certificate Signed
Status
01Possession Timeline
Proposed
Jul 2019
Revised
Jul 2019
Status
Ongoing
02Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 BHK233–332 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03RERA Trust Record
MahaRERA No.
P51700004551
Registered
2017-08-09
Litigation
None on record
Escrow Bank
THE KALYAN JANATA SAHAKARI BANK LTD.
Architect
Raj Associates
Total FSI
4349
04Buildings Β· 2 Wing(s)
E - Wing9 floors Β· β€” units
F - Wing9 floors Β· β€” units
05Land DNA Β· Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06Location
πŸ“ Ambarnath
19.177641000000001,73.241747000000004
β–Έ Explore map & Street View β€” for verified buyers
07Promoter & Professionals
SAI SAMRUDDHI CONSTRUCTION CONA
09Construction Progress49% avg
Basement (if any)100%
Excavation100%
Plinth100%
Slabs of Super Structure100%
Stilt Floor 100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Sanitary Fittings within the flats / premises10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Podiums (if any) 0%
10Amenities
Community BuildingsEnergy managemcntEnergy managementLandscaping & Tree PlantingLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And Disposal
12Floor Plans, E-Brochure & Payment Plans
πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13EMI Calculator
β€”
14More by Sai Samruddhi Construction Co
Sainath ResidencyBhandup West Β· Sold OutSainath VrindavanMulund East Β· Under ConstructionAyaanaTaloja Β· Under ConstructionAntalyaBelapur Β· Under ConstructionThe AvenueBelapur Β· Under ConstructionThe GatewayVashi Β· Under Construction
15MahaRERA projects nearby in Ambarnath
Pradhan Mantri Awas Yojana - Urban2352 unitsBalaji Uphomes673 unitsMANOHAR VIKAS SHREEJI PARAISO PHASE - 2578 unitsShreeji Milestone575 unitsSky Gardens At Godrej Vihaa495 unitsMohan Willows Iii492 unitsPatels Pristine432 unitsKrushna Vihar - Phase I426 unitsShreeji Square Phase I425 unitsTrident Woods423 unitsShreeji Meadows400 unitsTulsi Viraj394 units
?Frequently Asked Questions
When is possession of Heramb Park Phase Ii?

As per MahaRERA, proposed possession is Jul 2019, revised to Jul 2019.

Is Heramb Park Phase Ii RERA-registered?

Yes β€” MahaRERA registration P51700004551, registered 2017-08-09. No litigations on record.

Who is the developer?

Sai Samruddhi Construction Co β€” 112 projects tracked on Mumbai Property Exchange.

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Ambarnath β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
βœ“ MahaRERA P51700077356β˜… Featured
Lodha Group
Lodha Hanging Gardens, Dombivali
3 BHK, 4 BHK Β· β‚Ή16,400/sq.ft Β· Possession Dec 2027
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’