Project Information

RERA Certificate No.
PR1330002502053
Registration No.
ACK27082503012
Registration Date
2026-01-12
Developer
Al Saad Constructions Partnership
Project Bank
INDIAN BANK
Proposed Possession
2031-04-30
Total Units
29
Units Sold
1 (3%)
Buildings
2
Project Area
1922.50 sq.m
Total FSI
4350.03
Approved FSI
1864.83
MahaRERA QR
Hira Residency Phase Ii
MahaRERA โ€” PR1330002502053
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned3
๐Ÿ Habitable3
๐Ÿ”ขTotal Units28
๐ŸกResidential12
๐ŸขNon-Residential16
๐Ÿ—๏ธProposed Floors4
โœ…Sanctioned4
๐Ÿ Habitable3
๐Ÿ”ขTotal Units1
๐ŸกResidential1

Construction Progress

BUILDING A1 WING A AND WING B

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth200%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

BUILDING B1

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โฌœEnergy managemcnt
โœ…Fire protection and fire safety requirements
โฌœInternal Roads & Footpaths
โฌœLandscaping & Tree Planting
โœ…Open Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โฌœSolid Waste Management And Disposal
โœ…Storm Water Drains
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting