Project Information

RERA Certificate No.
P51700003444
Registration No.
REA51700016410
Registration Date
2021-09-09
Developer
NIRMITI CONSTRUCTIONS Partnership
Architect
Anish And Associates
Proposed Possession
2021-12-30
Revised Possession
2021-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
6155.00 sq.m
Total FSI
8365.00
Approved FSI
8365.00
MahaRERA QR
JEEVAN ASHA HEIGHTS
MahaRERA — P51700003444
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors15
Sanctioned15
🚗Open Parking10
📅Completion2020-12-31
🏗️Proposed Floors15
Sanctioned15
🚗Open Parking10
📅Completion2020-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 41.52000045776367 0 0 0
0%
1Bhk 41.869998931884766 0 0 0
0%
1Bhk 42.36000061035156 0 0 0
0%
2Bhk 56.689998626708984 0 0 0
0%
2Bhk 57.959999084472656 0 0 0
0%

Jeevan Asha Heights Bldg No A-1

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 41.52 6 5 1
83%
1 BHK 41.87 1 0 1
0%
1 BHK 42.36 11 10 1
91%
2 BHK 56.69 3 2 1
67%
2 BHK 57.96 1 1 0
100%

Jeevan Asha Heights Bldg No B/1

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 41.52 8 7 1
88%
1 BHK 41.87 1 0 1
0%
1 BHK 42.36 15 12 3
80%
2 BHK 56.69 9 7 2
78%
2 BHK 57.96 1 0 1
0%

Construction Progress

JEEVAN ASHA HEIGHTS BLDG NO A-1

Basement (if any)100%

Jeevan Asha Heights Bldg No A-1

Excavation100%

JEEVAN ASHA HEIGHTS BLDG NO A-1

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Jeevan Asha Heights Bldg No A-1

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

JEEVAN ASHA HEIGHTS BLDG NO A-1

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Jeevan Asha Heights Bldg No A-1

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

JEEVAN ASHA HEIGHTS BLDG NO A-1

Plinth100%
Podiums (if any) 0%

Jeevan Asha Heights Bldg No A-1

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

JEEVAN ASHA HEIGHTS BLDG NO A-1

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Jeevan Asha Heights Bldg No A-1

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

JEEVAN ASHA HEIGHTS BLDG NO A-1

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Jeevan Asha Heights Bldg No A-1

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

JEEVAN ASHA HEIGHTS BLDG NO B/1

Basement (if any)100%

Jeevan Asha Heights Bldg No B/1

Excavation100%

JEEVAN ASHA HEIGHTS BLDG NO B/1

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Jeevan Asha Heights Bldg No B/1

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

JEEVAN ASHA HEIGHTS BLDG NO B/1

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Jeevan Asha Heights Bldg No B/1

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

JEEVAN ASHA HEIGHTS BLDG NO B/1

Plinth100%
Podiums (if any) 0%

Jeevan Asha Heights Bldg No B/1

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

JEEVAN ASHA HEIGHTS BLDG NO B/1

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Jeevan Asha Heights Bldg No B/1

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

JEEVAN ASHA HEIGHTS BLDG NO B/1

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Jeevan Asha Heights Bldg No B/1

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.