J
✓ MahaRERA P52000014941RERA: no litigation reported16
Units
2022
Possession
1
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Dec 2022
Status
New
03
RERA Trust Record
MahaRERA No.
P52000014941
Registered
2021-09-09
Litigation
No reported in source
Escrow Bank
UNION BANK OF INDIA
Architect
Arsallan Pawalkar
Total FSI
511
04
Buildings · 1 Wing(s)
Jogilkar Heights6 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Sutarali Navenagar
18.082020799999999,73.422441000000006
18.082020799999999,73.422441000000006
▸ Explore map & Street View — for verified buyers
09
Construction Progress
33% avgBasement (if any)100%
Excavation100%
Plinth100%
Slabs of Super Structure60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsTreatment And Disposal Of Sewage And Sullage WaterWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory?
Frequently Asked Questions
When is possession of Jogilkar Heights?
As per MahaRERA, proposed possession is Dec 2022.
Is Jogilkar Heights RERA-registered?
Yes — MahaRERA registration P52000014941, registered 2021-09-09. The current MahaRERA source record reports no litigations.
Who is the developer?
Aijaz Ismail Darekhan View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.