List PropertyWhatsApp
New ProjectsBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your PropertyπŸ’¬ WhatsApp Us
πŸ† Mumbai's oldest property portalSince 1995βœ“ MahaRERA A51800043517βœ“ RERA-verified project data🟒 We reply in minutes on WhatsApp
M
βœ“ MahaRERA P51700004825βœ“ Clear

Munisuvrat Arc by Shree Munisuvrat Realty

Shree Munisuvrat Realty
πŸ“ Bhiwandi, Thane Β· 421302
72
Units
2019
Possession
2
Buildings
Certificate Signed
Status
01Possession Timeline
Proposed
Mar 2019
Revised
Mar 2019
Status
Ongoing
02Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Shop138–503 ftΒ²On request
2 BHK631 ftΒ²On request
3 BHK953–1,024 ftΒ²On request
4 BHK1,168 ftΒ²On request
4 BHK Type1,085–1,295 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03RERA Trust Record
MahaRERA No.
P51700004825
Registered
2017-08-09
Litigation
None on record
Escrow Bank
HDFC BANK
Architect
R R Consulting Ravish Abdul Rahman Dhuru
Total FSI
5931
04Buildings Β· 2 Wing(s)
Munisuvrat Arc - Building 1 Plot 114 floors Β· β€” units
Munisuvrat Royal - Building 2 Plot 213 floors Β· β€” units
05Land DNA Β· Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06Location
πŸ“ Bhiwandi
19.275266999999999,73.046291999999994
β–Έ Explore map & Street View β€” for verified buyers
07Promoter & Professionals
Shree Munisuvrat RealtyNA
09Construction Progress57% avg
Basement (if any)100%
Excavation100%
Plinth100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor 80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
10Amenities
Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationEnergy managemcntEnergy managementFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsStreet LightingWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12Floor Plans, E-Brochure & Payment Plans
πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13EMI Calculator
β€”
14More by Shree Munisuvrat Realty
Naman XanaWorli Β· Sold OutPoddar VasundharaVile Parle East Β· Under ConstructionAvenue 9Vile Parle West Β· Under ConstructionAshirwad ResidencyGhatkopar East Β· Under ConstructionYashreeThane Β· Ready to Move InShreejee MrugarchanaMulund West Β· Ready to Move In
15MahaRERA projects nearby in Bhiwandi
Dgt - Sector 3A - Cluster 2 - Phase 11836 unitsDosti Greater Thane - Sector 3A - Cluster 1B - Phase 11025 unitsUsha Residency1020 unitsNarayani Dham Building No 2A And 2B869 unitsDgt - Sector 3A - Cluster 2 - Phase 2830 unitsDgt - Sector 3A - Cluster 2 - Phase 3710 unitsDosti Greater Thane - Sector 3A - Cluster 1B - Phase 3682 unitsSIYARA AVENUE620 unitsMagus City Tower 1 Selene431 unitsSiyara Viva423 unitsArihant Aaradhya Phase Ii412 unitsAtlantic377 units
?Frequently Asked Questions
When is possession of Munisuvrat Arc - Building 1 Plot 1 And Munisuvrat Royal - Building 2 On Plot 2?

As per MahaRERA, proposed possession is Mar 2019, revised to Mar 2019.

Is Munisuvrat Arc - Building 1 Plot 1 And Munisuvrat Royal - Building 2 On Plot 2 RERA-registered?

Yes β€” MahaRERA registration P51700004825, registered 2017-08-09. No litigations on record.

Who is the developer?

Shree Munisuvrat Realty β€” 265 projects tracked on Mumbai Property Exchange.

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Bhiwandi β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
βœ“ MahaRERA P51700077356β˜… Featured
Lodha Group
Lodha Hanging Gardens, Dombivali
3 BHK, 4 BHK Β· β‚Ή16,400/sq.ft Β· Possession Dec 2027
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’