Noble HeightProject photos will appear here when available.
Project Information
RERA Certificate No.
P51700005322
Registration No.
REA51700011084
Registration Date
2021-09-09
Developer
Noble Constructions Partnership
Architect
Sameer S Lotke & Associations
Project Bank
INDIAN BANK
Proposed Possession
2023-03-30
Revised Possession
2023-03-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
3875.00 sq.m
Total FSI
4962.56
Approved FSI
4585.69
Noble Height
MahaRERA โ P51700005322
MahaRERA โ P51700005322
Scan to verify on MahaRERA portal
Wing-wise Details
๐๏ธProposed Floors6
โ
Sanctioned6
๐๏ธProposed Floors1
โ
Sanctioned1
๐๏ธProposed Floors21
โ
Sanctioned21
Apartment Configurations
NOBLE APARTMENT B-1
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 30.47 | 4 | 4 | 0 | 100% |
| 1 BHK | 32.4 | 4 | 4 | 0 | 100% |
| 1 BHK | 34.19 | 4 | 4 | 0 | 100% |
| SHOP 1 | 15.89 | 1 | 1 | 0 | 100% |
| SHOP 2 AND 3 | 19.42 | 2 | 2 | 0 | 100% |
| SHOP 4 | 11.8 | 1 | 1 | 0 | 100% |
| SHOP 5 | 14.22 | 1 | 1 | 0 | 100% |
NOBLE C1
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1RK | 39.39 | 1 | 0 | 1 | 0% |
NOBLE HEIGHT A-1
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 32.23 | 2 | 0 | 2 | 0% |
| 1 BHK | 32.33 | 54 | 25 | 29 | 46% |
| 2 BHK | 47.84 | 32 | 26 | 6 | 81% |
| SHOP A | 27.31 | 3 | 2 | 1 | 67% |
| SHOP B | 21.83 | 2 | 2 | 0 | 100% |
| SHOP C | 20.23 | 1 | 1 | 0 | 100% |
Construction Progress
NOBLE APARTMENT B-1
NOBLE C1
NOBLE HEIGHT A-1
RERA Registered Amenities
โฌAggregate area of recreational Open Space
โฌCommunity Buildings
โ
Electrical meter room, sub-station, receiving station30%
โ
Energy managemcnt25%
โ
Fire protection and fire safety requirements
โ
Internal Roads & Footpaths40%
โ
Landscaping & Tree Planting60%
โ
Open Parking
โ
Sewerage (Chamber, Lines, Septic Tank , STP)25%
โฌSolid Waste Management And Disposal
โ
Storm Water Drains25%
โ
Street Lighting
โ
Treatment And Disposal Of Sewage And Sullage Water
โ
Water Supply25%
โ
Water conservation /Rain water harvesting50%